CHANGE ORDER FORM
Change Order No. 1(FINAL)
Project Title 24 Place Sewer Replacement
Bid No. IFB 05/06 -05
Owner: City of Sanford
Contractor: Nile Underground Technologies, Inc.
Agreement Date: April 14 2006
This Change Order is necessary to cover changes in the work to be
performed under this Agreement. The GENERAL CONDITIONS,
SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS
apply to and govern all work under this Change Order.
THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS:
(1) Original Contract Price
(2) Current Contract Price (Adjusted by Previous Change Orders)
(3) Total Proposed Change in Contract Price
(4) New Contract Price (Item 2 + Item 3)
(5) Original Contract Time
(6) Current Contract Time (Adjusted by Previous Change Orders)
(7) Total Proposed Change in Contract Time
(8) New Contract Time (Item 6 + Item 7)
(9) New Contract Substantial Completion Date
$ 384,333.50
$ 384,333.50
$ (54,518.00)
$ 329,815.50
120 Days
No Change
No Change
120 Days
September 27, 2006
Page 1 of 3
Change 0rder#1
CHANGES ORDERED
ITEM 1
Description of Change:
Reason for Change:
Change in Contract Price:
Change in Contract Time:
Quantity Adjustments
Incorporate actual constructed quantities into the contract
($54,518.00)
0 Days
CHANGE ORDER SUMMARY
No.
Description
Change In
Contract Price
Change In
Contract Time
1
Quantity Adjustments
($54,518.00)
0 Days
TOTAL
($54,518.00)
0 Days
WAIVER This Change Order constitutes full and mutual accord and satisfaction for the
adjustment of the Contract Price and Contract Time as a result of increases or decreases in
cost and time of performance caused directly and indirectly from the change. Acceptance of
this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change
Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall
waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution
of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction
that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change
Order.
Page 2 of 3
Change 0rder#1
APPROVAL AND CHANGE ORDER AUTHORIZATION
ACKNOWLEDGMENTS
The aforementioned change, and work affected thereby, is subject to all provisions of the
original Agreement and specifically changed by this Change Order; and
It is expressly understood and agreed that the approval of the Change Order shall have no
effect on the original Agreement other than matters expressly provided herein.
ATTEST: Nile Underground Technologies, Inc.
Contractor
Timothy R. Dennard, Jr. - President
(Secretary) Printed Name and Title f fficer
/- -vo
Date y (Signature)
//-,? - C24
(Corporate Seal) Date
ATTEST: City of Sanford
Owner
���� - ' Robert P. Yehl - City Manager
Signature) Printed Name and Title
qJf4 Iwo
Date By (Signatu
(Seal) Date
END OF SECTION
Page 3 of 3
Change Order#1
CITY OF SANFORD
24TH PLACE SEWER REPLACEMENT
CPH PROJECT NO. S0670.01
CHANGE ORDER NO 1 - ATTACHMENT
I I — -
DESCRIPTION
UNITS
QUANTITY
UNIT COST
TOTAL COS
Mill Existing Pavement US 17 -92) (1 ")
1" FC -3
SY
SY
- 421.00
- 421.00
$11.00
$35.00
$ 4,631.00)
$ 14,735.00
1.5" Type S Asphalt
SY
372.00
$17.00
$ 6,324.00
Cut, Grout, and Cap Existing Sewer 12" Dia.)
Cut, Grout, and Cap Existing Sewer (6" Dia.)
LF
LF
- 250.00
-31.00
$70.00
$65.00
$ 17,500.00
$ 2,015.00)
12" D.I. Force Main Pipe From S -2 to S-4
LF
- 114.00
$75.00
$ 8,550.00)
12" PVC Sanitary Sewer 6' -8' Depth)
LF
101.00
$48.00
$ 4,848.00
14" x 14" Tapping Sleeve and Valve
EA
-0.961
$19,000.00
$ 18,259.00
/GA GAO nn%
TOTAL
Original Contract Amount
$384,333.50
Proposed C.O. No. 1
($54,518.00)
Proposed New Contract Amount
$329,815.50
CITY OF SANFORD
24TH PLACE SEWER REPLACEMENT
CPH PROJECT NO. S0670.01
CHANGE ORDER NO 1 - ATTACHMENT
TIME SUMMARY
TIME CHANGE
ITEM 1 - QUANTITY ADJUSTMENTS 0 Da s
TOTAL Days
CONTRACT TIME SUMMARY
Contract Time 270 Days
Proposed Change in Contract Time No Change
New Contract Time No Change
Date of Notice to Proceed
5/30/2006
Total Adjusted Contract Time
120 Days
Substantial Completion Date
9/27/2006
Contract Time From Substantial Completion to Final Completion
30 Days
Final Completion Date
10/27/2006