CHANGE ORDER FORM
Change Order No. 1
Project Title Cloud Branch Drainage Improvements - Ph. 2
Bid No. IFB 08/09 -14
Owner: City of Sanford
Contractor: Central Florida Environmental Corp.
Agreement Date: August 31 2009
This Change Order is necessary to cover changes in the work to be
performed under this Agreement. The GENERAL CONDITIONS,
SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS
apply to and govern all work under this Change Order.
THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS:
(1) Original Contract Price
(2) Current Contract Price (Adjusted by Previous Change Orders)
(3) Total Proposed Change in Contract Price
(4) New Contract Price (Item 2 + Item 3)
(5) Original Contract Time
(6) Current Contract Time (Adjusted by Previous Change Orders)
(7) Total Proposed Change in Contract Time
(8) New Contract Time (Item 6 + Item 7)
(9) New Contract Substantial Completion Date
2.358.902.00
$ 2,358,902.00
$ 225,928.46
$ 2,584.830.46
180 Days
180 Days
97 Days
277 Days
7/2/10
Page 1 of 6
Change Order #1 4 -29 -10
CHANGES ORDERED
ITEM 1
Description of Change:
Reason for Change
Change in Contract Price:
Change in Contract Time
Revision of project sign
ARRA funded job required specific project sign to be installed at
project site.
$140.00
0 Days
ITEM 2
Description of Change
Reason for Change
Change in Contract Price:
Change in Contract Time
Remove an existing end wall and build a new end wall
The existing endwall located in the Cloud Branch Ditch near 6
Street needs to be removed and rebuilt to accommodate the shift
and regrading of the ditch.
$3,989.31
6 Days
ITEM 3
Description of Change:
Reason for Change
Change in Contract Price
Change in Contract Time
Relocation of reclaimed water main (RWM) connection
The reconnection of the RWM had to be moved because the
existing RWM pipe location was not where it was shown to be.
$6,467.94
3 Days
Change Order #1 4 -29 -10
Page 2 of 6
ITEM 4
Description of Change: Additional contaminated soil haul off and dump fees, excavation
beyond the original defined contaminated limits and earthwork
deduction.
Reason for Change: Contaminated soil were discovered and removed beyond the
initial limits provided in the geotechnical report.
Change in Contract Price: $163,260.31
Change in Contract Time: 30 Days
ITEM 5
Description of Change:
Upgrade the electrical service to Coast Line Park
Reason for Change:
To provide a larger amp service for future lights or development in
the park.
Change in Contract Price:
$16,909.15
Change in Contract Time:
14 Days
ITEM 6
Description of Change: Pond excavation and inlet installation
Reason for Change: Need to add an inlet and a pond to collect flow between railroad
tracks between 6 Street and 8 Street.
Change in Contract Price: $24,370.70
Change in Contract Time: 25 Day
ITEM 7
Description of Change: Additional clearing and grubbing
Reason for Change: Contractor had to clear and grub an additional .25 acres near 6th
Street for the relocation of the Cloud Branch Ditch. There is
already a pay item for clearing and grubbing.
Change in Contract Price: $908.00
Change in Contract Time: 1 Day
Page 3 of 6
Change Order #1 4 -29 -10
ITEM 8
Description of Change:
Reason for Change:
Change in Contract Price
Change in Contract Time
Additional concrete for 4'X13' B.C. end wall
Additional concrete was needed to finish the footer and end wall.
$2,803.50.00
0 Days
ITEM 9
Description of Change:
Reason for Change:
Change in Contract Price:
Change in Contract Time:
Additional removal of existing 24" storm pipe
Additional pipe was found and removed during excavation.
$1,396.85
0 Days
ITEM 10
Description of Change:
Reason for Change:
Change in Contract Price:
Change in Contract Time:
Additional removal of existing 15" storm pipe
Additional pipe was found and removed during excavation.
$366.00
0 Days
ITEM 11
Description of Change:
Reason for Change:
Change in Contract Price:
Change in Contract Time:
Additional removal of 8" abandoned water main
Additional pipe was found and removed during excavation.
$5,316.70
0 Days
Change Order #1 4 -29 -10
Page 4 of 6
ITEM 12
Description of Change
Reason for Change
Change in Contract Price
Change in Contract Time
Delay of jack and bore
CSX flagmen were not available at contractors time of proposed
time of jack and bore
"ME
18 Days
CHANGE ORDER SUMMARY
No.
Description
Change In
Contract Price
Change In
Contract Time
1
Revision of project sign
$140.00
0 Days
2
Remove an existing end wall and build a new end
wall
$3,981.31
6 Days
Y
3
Relocation of reclaimed water main (RWM)
connection
$6,467.94
3 Days
4
Additional contaminated soil haul off and dump
fees, excavation beyond the original defined
contaminated limits and earthwork deduction.
$163,260.31
30 Days
5
Upgrade the electrical service to Coast Line Park
$16,909.15
14 Days
6
Pond excavation and inlet installation
$24,370.70
25 Days
7
Additional clearing and grubbing
$908.00
1 Days
8
Additional concrete for 4'X13' B.C. end wall
$2,803.50
0 Days
9
Additional removal of existing 24" storm pipe
$1,396.85
0 Days
10
Additional removal of existing 15" storm pipe
$366.00
0 Days
11
Additional removal of 8" abandoned water main
$5,316.70
0 Days
12
Delay of jack and bore
$0.00
18 Days
TOTAL
$225,928.46
97 Days
Change Order #1 4 -29 -10
Page 5 of 6
WAIVER This Change Order constitutes full and mutual accord and satisfaction for the
adjustment of the Contract Price and Contract Time as a result of increases or decreases in
cost and time of performance caused directly and indirectly from the change. Acceptance of
this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change
Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall
waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution
of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction
that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change
Order.
APPROVAL AND CHANGE ORDER AUTHORIZATION
ACKNOWLEDGMENTS
The aforementioned change, and work affected thereby, is subject to all provisions of the
original Agreement and specifically changed by this Change Order; and
It is expressly understood and agreed that the approval of the Change Order shall have no
effect on the original Agreement other than matters expressly provided herein.
ATTEST
(Secretary)
to
Date
Date
Central Florida Environmental Corr).
Contractor
-YJ sWCJw 7 2-114.
PrinW Name and Title of Officer
Ely (Signature)
(Corporate Seal) Date
ATTEST: City of Sanford
Owner
WY Tom George — Interim City Manager
(Signature) Printed Name and Title
Date By (9i ture)
(Seal) Date
END OF SECTION
Page 6 of 6
Change Order #1 4 -29 -10