1393 Ft. Mellon Cert of CompL�
PURCHASING DEPARTMENT
T RANSMITTAL MEMORANDUM
To: City Clerk
RE: Certificate of Substantial Completion Section 00626 Ft Mellon Maintenance Facility
EO Koch Construction Co., IFB 10/11 -02
The item(s) noted below is /are attached and forwarded to your office for the following action(s):
❑ Development Order
❑ Final Plat (original mylars)
❑ Letter of Credit
❑ Maintenance Bond
❑ Ordinance
❑ Performance Bond
❑ Resolution
Mayor's signature
Kenaenng I
Safe keeping (Vault)
Lj Payment Bond
❑ City Manager Signature
❑ City Clerk Attest/Signature
Once completed, please:
❑ Return originals to Purchasing
❑ Return copies
Special Instructions:
c
Marisol Ordonez
From
Date
TADept_ forms \City Clerk Transmittal Memo - 2009.doc
SECTION 00626
CERTIFICATE OF SUBSTANTIAL COMPLETION
Project Title Ft. Mellon Maintenance Facility
Bid No. IFB 10/11 -02
Owner: City of Sanford, Florida
Contractor: E. O. Koch Construction Company
Agreement Date: MU 26 2011
This Certificate of Substantial Completion applies to all work under the Contract Documents or
the following specified parts thereof if construction is phased by contract:
ISSUED TO:
Contractor: E. O. Koch Construction Company
P.O Box 1965
Sebring, FI 33871
The work to which this Certificate applies has been inspected by authorized representatives of
Contractor and Owner and that Work is hereby declared to be substantially completed in
accordance with the Contract Documents on:
January 23, 2012
Date of Substantial Completion
A list of items to be completed or corrected is attached hereto. This list may not be all- inclusive,
and the failure to include an item in it does not alter the responsibility of Contractor to complete
and warrant all the Work in accordance with the Contact Documents. All items on the list shall
be completed or corrected by Contractor within 30 days of the above date of Substantial
Completion.
00626 -1
This Certificate does not constitute an acceptance of Work not in accordance with the Contract
Documents nor is it a release of Contractor's obligations to complete the Work in accordance
with the Contract Documents.
Executed by City of Sanford on
�'?' / C;2 0f
Date
City of Sanford Representative: Norton N. Bonaparte Jr.
By:
(Signature)
Norton N. Bonaparte Jr. / City Manager
(Printed Name and Title)
Contractor accepts this Certificate of Substantial Completion on 2/17/2012
Date
Contractor: E. O. Koch Construction Com
By:
(Sig a u
Clarence E. Polston, Vice President
(Printed Name and Title)
END OF SECTION
00626 -2