Loading...
1121-Prime Const-Cloud Branch-Work Directives 1-7S SECTION 00945 WORK DIRECTIVE CHANGE FORM Work Directive No.: Name of Project: Cloud Branch Drainage Improvements - Ph. 1 (IFB 05/06 -08) Effective Date: Owner: City of Sanford Contractor: Prime Construction Group, Inc. Description of Change: See Attached Reason for Change: See Attached If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based thereon will involve one of the following methods of determining the effect of the change(s). Method of Determining the Change in Contract Price Time and Materials X Unit Prices Cost Plus Fixed Fee Other Method of Determining the Change in Contract Time Contractor's Records Engineer's Records X As Specified Below Other Estimated ;^^r „�vFease (decrease) in Contract Estimated increase (decrease) in Contract Price = ($57,417.00) . If the change Time = 0 days. If the change involves an additional increase, estimated involves an additional increase, estimated amount is not to be exceeded without time is not to be exceeded without further further authorization. authorization. Recommended B CPH Engineers, nc. Date SPECLIB062703 00945 -1 Executed By: Owner'UAWhorizeN Reore, erlative Contractor's Authorized resentative Roy W. Smith, Jr resident Prime Construe n Group, Inc. END OF SECTION 24 10 I®A Date Date (39945 -2 SPECLIB062703 WORK DIRECTIVE NO. 1- Summary of Changes ITEM 1 — Modified 4 X11 Box Culvert at FPL Transmission Pole Description of Change: The 4 X11 box culvert between 11 St and 12 St was modified to deflect around an existing FPL Transmission Pole, since FPL is not able to relocate the existing pole (pole is too large for FPL to relocate). The change includes adding an additional manhole access at the deflected section, extra work needed to work around the pole, and an increase to the overall box culvert length. Reason for Change: To accommodate existing FPL Transmission Pole Change in Contract Price: $11,857.00 Change in Contract Time: 0 Days ITEM 2 — Deletion of S -27 & S -28, and Modification to 5 X 5 Box Culvert Location. Description of Change: Structures S -27 and S -28 were deleted and 45 degree bends along with manhole access points were added to the box culvert. The 5 x 5 box culvert was also shifted approximately 20' toward the west to minimize utility relocations. Reason for Change: Easier to construct and provided a cost savings to the City. Change in Contract Price: ($55,534.00) Change in Contract Time: 0 Days ITEM 3 — Delete Structure 5 -36 and Add Modified Box Culvert with P -6 Riser Description of Change: Type J -6 curb inlet structure S -36 was deleted and a modified box culvert section was added with a P -6 riser and inlet top. Reason for Change: Easier to construct and provided a cost savings to the City. Change in Contract Price: ($1,597.00) Change in Contract Time: 0 Days Page 1 of 2 ITEM 4 - Delete Structure S -35 and Add Modified Box Culvert with Riser, Ring and Cover Description of Change: 14 x 9 conflict Junction Box S -35 was deleted and a modified box culvert section was added with a manhole access point. The conflict will be installed through the box culvert section. Reason for Change: Easier to construct and provided a cost savings to the City. Change in Contract Price: ($12,143.00) Change in Contract Time: 0 Days Page 2 of 2 W U n I � i U Z :0 0 I [ - Y) W _0 Q 2 U LL ry 0 D U) (D O 0 N 00 2:E C) C) � Cl) 0 LO M 0) d r' Z O LO LO r Q U r co L.0 64 r LO v 69 -' 64 1 1 I69 O 0 0 0 0 0 0 0 0 O O 0 0 i- O 0 0 0 0 0 0 0 0 O O O O Z 1-� O M O ti N U O M CD LC) ti In "It (0 O O O Lo O Cc O Lf) LS O 0 1-- co LO O � O 00 p r O r In r L17 .... r Ln ti Lr7 O r- Q CO N � 64 , 6F} � 64 64 64 C14 64 64 C O C) O O C O O O C) O O O O c0 O 0 0 0 0 0 0 0 0 O O O O O ~ W ti 0 0 0 0 U*) O O O O co O 1- ( a LO O m O 64 N LO N� O O O U') Z _U 00 O r CD 64 N r 64 O ct O 00 Y Q a. r lf) 1 -- �} 64 69 1` LLB O f- U Q r � 69 64 6R N 64 i� Z J LU LU -i W fn CO J J W W O D `O N M C� O 1-- M ti D) L) U ' , r N C,4 N ''t M C r r r r ' r L ca C O U a) CD Z O W E O > O C H `�- a) ui E Q , W v m Y O U "O C ~ U) OL O cc c� r N io i L CD O W C O O o ai U a� > Q L > o d 0 C U Y LO 05 > Q J °6 Q U) O (0 .- > Y U6 C O O -0 O D_ . F, CL7 p d L. a) 'O Q J N r- N p •O Z Q) CU 7 E � cC0 a) o a) O a) I co 0 cn N U U) O J v Z W O. C .c Q7 c CD a m Co — W 3 Q CO N p O U) Q Y CU a) c� O •� E (q c a), � L Q o ° a d$ C E C p J a) CD C N I = (6 O a) r N i E a) E a) N a �LO E U JQ. o L o r X U) y - @ _ a) tII fl a) M I w L �, co (�6 7 !CD cu L) ` 0 a) X� O a) �) �� L I a) a) > Y O a) O CD 1 ` a) H �' I N O (6 x > Him CD C�> > a) > .X'io _ �N O c> O c Oil > n a W x iU W o'J �� x U x CL) I �. c .� �W c x W IC x p. E N o J O CIO :5 m 'm x >�= �, ] U O Imo, 71 J �'� 0 C O' Q.� U J a) � J ' I a) U J cJi� � (Q OIL ''. a) N O a) U O) , (D LO C C a)' I � (>3 Q) i J . a) I (� X X 01 �I �o X,'^ C) xl L �' Lni S 0I a O O v� I > O X! O O Im O �tO i l , olf- m, as �� a); y� CL) w: a� aim �� o o� , x l x i a� X I X a� °— a� ID Q tt) 1]'Q o 0'� Q D Q M 0 1 < 1 et Q O O O �-- J F- N c') M I Lo, J c') M'V CD N CD a) I O - D L) Q Q 10 C U r r Q (D O 0 N 00 2:E SECTION 00945 WORK DIRECTIVE CHANGE FORM Work Directive No.: 2 (Revised) Name of Project: Cloud Branch Drainage Improvements - Ph. 1 (IFB 05/06 -08) Effective Date: Owner: City of Sanford Contractor: Prime Construction Group, Inc. Description of Change: Modify 4 x 11 box culvert at existing gravity sewer and replace 40 LF of existing 8" sanitary sewer with new 8" DI sewer at 11 Street. Reason for Change: The existing sewer line was encountered while installing_ the 4x11 box culvert across 11 street. At the City's request, the new box culvert was then modified and the sewer was changed from clay to ductile iron in the conflict area. If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based thereon will involve one of the following methods of determining the effect of the change(s). Method of Determining the Change in Contract Price Method of Determining the Change in Contract Time Time and Materials X Unit Prices Cost Plus Fixed Fee Other Estimated increase (decrease) in Contract Price = $8,934.71 If the change involves an additional increase, estimated amount is not to be exceeded without further authorization. Contractor's Records Engineer's Records X As Specified Below Other Estimated increase (desrease) in Contract Time = 1 days. If the change involves an additional increase, estimated time is not to be exceeded without further authorization. 00945 -1 SPECLIB062703 Recommended CPH Engineer c. Executed By: Owner's Authorized Representative n/a9 /�c. Date / ?- / . 10 !o Date 1zlefo� Contractor's Authoriz epresentative Roy W. Smith ., President: Prime Constr ion Group, Inc. END OF SECTION Date 00945 -Z SPECLIB062703 - PRIME CONSTRUCTION GROUP, INC. CGCO 37504 . CU CO516650 QB33325 1000 Jetstream Drive, Orlando, FL 32824 407 -856 -6180 PH P.O. Box 590507, Orlando, FL 32859 -0507 (Mailing Address) 407- 856 -8182 FX November 17, 2006 CPH Engineers 500 West Fulton Street Sanford, FL 32771 Attn: Rocco Nasso, P.E. j I �) 530- 02 -005R RE: Cloud Branch Drainage Improvements -- Phase I City of Sanford Project No.: 05106 -08 Prime Construction Group, Inc. Job No. 530 CO. Proposal to replace existing 8" sanitary sewer with new Dl sewer on 11 St - Revised Dear Rocco: Attached please find the Revised Change Order Proposal to modify 4 x 11 box culvert and replace 40 LF of existing 8" sanitary sewer with new 8" DI sewer at 11 th Street. The above sewer line was riot shown in the plans and encountered while laying the above box culvert on 11 St. This proposal includes. all labor, material, equipment and subcontractor costs for the following: • Modify 4 x 11 box culvert - $ 4,13 1.71 Replace 8 ",-sanitary sewer. with new 8" DI .sewer - Increase Pay Item # 144 quantity by 40 LF at $120.00 /1-17 - $4,800:00 The total.value.of the above .proposal is valued at and one (1) additional day. The above" revision was discussed with- City of. Sanford. in the progress meeting on November 14, 2006. * Also, PCG to disregard W DC No. 2 form dated November 08, 2006 sent by CPH for execution. If you have any questions regarding the Change Order Proposal, please do not hesitate to call. Sincere) ? c eta Patel Project Manager KP!pa c FAPrcject_ManagementUobs\530 Cloud Branch Drainage Imp. Phase l\02Correspondenc6\To -from Engineer CPM005R CO Proposal for relocating sanitary sewer at 1 I th St : Revised.doc Change Order Proposal Change Request No,: -53.0-04-Revised.-.- ........Date: i7- Nov_ -06 Owner Reference: Description: Modify 4x11 Box Culvert and Replace 8" Sanitary Sewer on 11th St. Crew Size Ouantity Unit Unit Price Extension PCG Labor with Burden 1 Modify 4 x 11 Box Culvert on 11th SL toaccommodate existing Foreman, Pipe 1 1.5 Days $489.00 $733.50 8' sanitary sewer line Pipe Layer . 1 1 Days $336.00 $336.00 Pipe Tallman 1 I Days $294.00 $294.00 Pipe Laborer i 1 Days $273.00 $273.00 Operator, Track Excavator 1 2 Hn; $36.00 $72.00 Operator, Loader 1 2 Hrs $29.00 $58.0D 3 CG Labor Subtotal $1,766.50 PCG Labor Markup 15.00% $264.98 Materials 1 Concrete 1.5 CY $116.OD $174.00 4aterial Subtotal $174.00 Material Tax 6.50 °6 $11.31 Material Markup 115.00% $27.80 Equipment and Other Rentals Modify 4 x 11 Box Culvert on 11th St. to accommodate existing Excavator, PC 300 0.25 Day $980.00 $245.00 8' sanitary sewer line Pickup Truck & Cell Phone 1.5 Day $175.00 $262.50 Loader, JD 644 - 4 CY . 025 Day $765.00 $19125 tental Subtotal $698.75 Rental Tax 6.50% $45.42 - Rental Markup 15.00% $111.63 subcontracts 1 Conciete Cutting and Breaking - Saw Cut 4xi 1 Box Culvert 1 LS $(100.01) $800.00 subcontractor Subtotal $600.00 Subcontractor Markup 5.00% $4000 Change Order Subtotal $3.940.38 Daily Jobsite Overhead 1.00 Days $159.00 $159.00 Small Tool Allowance 2.00% $1,766.50 $35.33 $4,134.71 Bv,+a- r+nrs'Jflt' 2.00:6 Change Order Subtotal E4 Pa stem 4 144' lncre 40 LF $120.00 a8.dG0 -00 Change Order Grandlotal C&43,'..4A tdditlonai Contract Time requested 1 bay o r 134.71 'his estimate is valid for 30 days. :W rojeet_ \WnsgemenNobslS30 Cls�d B.anch tmp. Ph ess hUtPSyAppfGaEpns4P ayApp &elensllPsyAPpkapon ].wWN G7tU Orlando, FL 32824 (� Phone 407.856.0997 Fax 407,956.0798 Florida CGC- 061534 '. CCB Orlando order-I . J ob:oca "°" 13th and Lake Street cay9tate Sanford, FL Job Phone P.O. F ,. 005322 °a10mQ Prime Construction Grou Name. p Job Ordered Q Job k Sweet Address PO BOX 590507 - . Dale Ordered_ G tystata,2r� Orlando, FL 32859 -0507 Q Order Taken Slad Date 10/27/06 & 10130/06 Perron, Reauestin' Hid Due Date Direallons 7o Jotaft _ jcayrrme (mice Y 407.877.1$00 Dale 0"oled Fax Y comment: Quoted By Description of Work unit Amount - Ouantity Well Saw GaS Slab Saw Elae SS Demolition Rem"'ll� Elea Drill .... liyd Dnll Wire Saw .. . Curb Saw Hyd Hand Saw Chain Saw, Oifiar 520.00 220.00 .60.00: 11 linear feet of 12" concrete wall sawin $25.00 $275.00 7 linear feet of 16 concrete wall sawing $35.00 $245.00 2 plunge cuts with 24" hand saw in corners of box to complete horizontal cut $30.00 $60.00 4 4" diameter core drill x 12" concrete box top $55,00 $220.00 Mileage Cha e Total N/C $800.00 SECTION 00945 Work Directive No.: Name of Project: Effective Date: Owner: Contractor: WORK DIRECTIVE CHANGE FORM 3 Cloud Branch Drainage Improvements - Ph. 1 (IFB 05/06 -08) City of Sanford Prime Construction Group, Inc. Description of Change: Install new Ditch Bottom Inlet south of S -15 along with 16 LF of 24" RCP Also modify Wingwail at S -15 to accommodate 24° RCP. Reason for Change: The existing ditch along the east side of Lake Avenue needed to be connected to the 3 x 7 box culvert crossing to eliminate erosion behind structure S -15. If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based thereon will involve one of the following methods of determining the effect of the change(s). Method of Determining the Change in Contract Price Time and Materials X Unit Prices Cost Plus Fixed l=ee Other Estimated increase ( �'�se ) in Contract Price = $8,136.12. If the change involves an additional increase, estimated amount is not to be exceeded without further authorization. Method of Determining the Change in Contract Time Contractor's Records Engineer's Records X As Specified Below Other Estimated increase (decrease) in Contract Time = 1 days. If the change involves an additional increase, estimated time is not to be exceeded without further authorization. 4 00945 -1 SPECLIS062703 Rec rnmendea B CPH Enginee , Inc. m /zflo( Date z Z , /; A 4 Date (Z1r. Ia& Contractor's Authorized Roy W. smith Prime Constr Date END OF SECTION 00945 -2 SPECLIB062703 Executed By: PRIME CONSTRUCTION GROUP, INC CGCO37504 CUCO56650 OB33325 1000 Jetstream Drive, Orlando, FL 32824 407- 856 -8180 PH P.O. Box 590507, Orlando, FL 32859 -0507 (Mailing Address) 407- 856 -8182 FX November 14, 2006 CPH Engineers 530 -02 -006 500 West Fulton Street Sanford, FL 32771 Attn: Rocco Nasso, P.E. RE: Cloud Branch Drainage Improvements — Phase I City of Sanford Project No.: 05106 -08 Prime tonstruction Group, Inc. Job No. 530 CO Proposal for new DBI on Lake Ave S -15A Dear Rocco: Attached please find the Change Order Proposal to install new Type D Ditch Bottom Inlet and 24' RCP to connect the ditch along East side of Lake Ave with 3 x 7 box culvert crossing. The above work was discussed with City of Sanford the'progress meeting in. October. The decision was made to install the above to eliminate erosion behind wingwall at S- This propo'sal'_includes all labor, material and equipment costs for the following: Modify wingwall at S -15 to accommodate 24" RCP Install DBI S-1 5A and 1 LF of 24" RCP . �Z13L. /A The total value of the above proposal is valued at and increase in contract time by one (1) additional day. If you have any questions regarding the Change Order Proposal, please do not hesitate to call. Sincere[ - Patel Pr Project Manager KPlpac FAProject Management\Jobs \530 Cloud Branch Drainage Imp. Phase 1\02Correspozidence \To -from Engineer CPH\006 CO Proposal for New DBI on Lake Ave S- 15A.doc '' Change Order Proposal Dhange Request No.: 530 -05 Date: 13- Nov -06 D�vner Deference: Description: New DBI on Lake Ave S-1 5A Crew Size Quantity Urtft Unit Price Extension ECG Labor with Burden 1 Install 16 LF of 24' RCP through S -15 Wingwall and Set DBI Foreman, Pipe 1 1 Days $489.00 $489.00 S -15A South of 3x7 Box Culvert on Lake Ave Pipe Layer 1 1 Days $336.00 $336.00 Pipe Laborer 1 1 Days $273.00 $273.00 Pipe Tallman 1 1 Days $294.00 $294.00 Operator, Track Excavator 1 1 Days $399.00 $399.00 Pipe Layer 1 1 Days $336.00 $336.00 Foreman, Carpenter 1 3 Hrs $61.00 $183.00 Concrete Finisher 1 3. Hrs $52.00 $156.00 Concrete Finisher Helper 1 3 Hrs $52.00 $156.00 CG Labor Subtotal $2,622.00 PCG Labor Markup 15.06% $393.30 Vlaterials 1 24' RCP 16 LF $25.36 $405.76 1 S-1 5A Type D Ditch Bottom Inlet with non - traffic grate 1 EA $1,302.09 $1,302.09 1 Mud and Brick 1 LS $200.00 $200.00 aterial Subtotal $1,907.85 Material Tax 6.50% $124.01 Material Markup 15.00% $304.76 Equipment and Other Rentals 1 Install 16 LF of 24' RCP through S -15 Wingwall and Set DBI Excavator, PC 300 1 Day MOM $980.00 S-1 SA South of 3x7 Box Culvert on Lake Ave Loader, JD 644 - 4 CY 1 Day $765.04 $765.00 Pickup Truck & Cell Phone 1 Day $175.00 $175.09 Plate Compactor, 13K Force 1 Day $115.00 $115.00 Pickup Truck & Cell.Phone 0.375 Day $175.00 $65.63 ental Subtotal $2,100.63 Rental Tax 6,50% $136.54 Rental Markup 15.00% $335.57 Subcontracts ibcontractor Subtotal Subcontractor Markup 5.00% Change Order Subtotal $7,924.68 Daily Jobsile Overhead 1.00 Days $159.00 $159.00 Small Tool Allowance 2.00% $2,622.00 $52.44 S8.136 12 �8ef>d,4rr�dnt Q-ee" -*� a Change Order G; andtetal Es as &s� ddltional Contract Time requested 1 Day its estimate is valid for 30 days. . 'rojeer_Managemen Nobs' Cloud a D tram ape Imp. Phasa rw^ OCDst ManapemMftChanga Drdem) :CDPrepDul5 Ne DOI on take Ave$•95AXL510henne Shur SECTION 00945 WORK DIRECTIVE CHANGE FORM Work Directive No.: 4 (Revised Name of Project: Cloud Branch Drainage Improvements - Ph. 1 (IFB 05/06 -08) Effective Date: Owner: City of Sanford Contractor: Prime Construction Group, Inc. Description of Change: Dispose of contaminated soil stockpiled on the Pond 5 site. 729.15 tons of Contaminated Soil was loaded and hauled to Soil Treatment Services Inc. in Kissimmee, FL. (see attached deliver tickets and hauling invoice) Reason for Change: The contaminated soil was removed from Coastline Park during the construction of the new ditch. The Contractor was unable to use the soil due to the presence of petroleum contaminate. If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based thereon will involve one of the following methods of determining the effect of the change(s). Method of Determining the Change in Contract Price Method of Determining the Change in Contract Time Time and Materials X Unit Prices ($57.36 /TN) Cost Plus Fixed Fee Other Estimated increase ( in Contract Price = $42,374.04 If the change involves an additional increase, estimated amount is not to be exceeded without further authorization. Contractor's Records Engineer's Records X As Specified Below Other Estimated increase ( '� i �e) in Contract Time = 3 days. If the change involves an additional increase, estimated time is not to be exceeded without further authorization. 00945 -1 SPECLIB062703 Re co mended By: C H Engineers, I �. Executed By: Owner's Auto ntative Contractor's Aulh presentative Roy W. Smith END OF SECTION Prime Construction Group, Inc. SPECLIB062703 1 1; Date Date . 2 -23 - o-i Date A '1 PRIME CONSTRUCTION GROUP, OUP, I N C -_ - - - -- CGCO37504 === CUCO56650 -- 0833325 __ 1000 Jetstream Drive, Orlando, FL 32824 407- 856 -8180 PH P.O. Box 590507, Orlando, FL 32859 -0507 (Mailing Address) 407- 856 -8182 FX January 23, 2007 CPH Engineers 500 West Fulton Street Sanford, FL 32771 Attn: Rocco Nasso, P.E. RE: Cloud Branch Drainage Improvements — Phase I City of Sanford Project No.: 05/06 -08 Prime Construction Group, Inc. Job No. 530 Dispose Contaminated Dirt — Final Cost Dear Rocco: 530 -02 -013 Per our letter regarding disposal of contaminated dirt dated January 3, 2007, all the extra work associated with the above has been completed. Total quantity of contaminated dirt delivered to Sail Treatment Services (STS) for incineration is 729.15 TN. The unit price quoted for the above work was $57.36/TN. Since the quantity of material went over 700 TN, STS performed two (2) additional pre - burn samples at $225 /EA. Also there is a $100.00 charge for trash in loads (See attached invoice for more details). Hence, the total cost to dispose contaminated dirt from pond 5 is $42,374.04. Please issue the work directive change for the above work at your earliest convenience. If you have any questions regarding the above costs, please do not hesitate to call. Sincerely, Ka to, n"PateI Project Manager KP /kp ',t�mieet hi�nae n eni�Yobc\ 3t? Cloud Bmnc#h Drainage Imp, Phase Engin,°er t_ PE4V113 r'�ispose =-taminated dirt - Final Cost.dod Change Order Proposal . - -- - - - -- - - - - Change Request No.: 530 -07 Dat, Owner Reference: Description: Load and Haul Contaminated Dirt from Pond 5 to Soil Treatment Services in PCG Labor with Burden 1 Load contaminated dirt from Pond 5 Foreman, Dirt 1 2 Days $489.00 $978.00 Operator, Loader 1 3 Days $315.00 $945.00 $1,923.00 PCG Labor Subtotal PCG Labor Markup 15.00% $2B8.45 Materials Material Subtotal Material Tax 6.50% Material Markup 15.00% Equipment and Other Rentals 1 Load contaminated dirt from Pond 5 Loader, JD 644 - 4 CY 3 Day $765.00 $2,295.00 Pickup Truck 8 Cell Phone 2 Day $175.00 $350.00 $2,645.00 Rental Subtotal Rental Tax 6.50% $171.93 Rental Markup 15.00% 5422.54 Subcontracts 1 Haul contaminated did to Soil Treatment Services, Kissimmee, 417 TN $18.00 $7,506.00 1 Soi! Treatment Services - Dispcsal Fee 417 TN $23.00 $9,591.00 $17.097.00 Subcontractor Subtotal Subcontractor Markup 5.00% $954.85 Change Order Subtotal $23.402.76 Daily Jobslte Overhead 3.00 Days $159.00 S477,DC Small Tool Allowanca 2.00% $1,923.00 $38.46 523.918.22 Bond Amount 2.00% 3411111906- Change Order Granetotal � Price Pr>r TN Aocontnna! I,ontrvct i eme reauestettt This estimate is VaUd for 30 days. r V ,.j-r_ e—&. D1.0-0� I Dar. n &P-. Shw If - - I T�ild -3 -F 07 11:54A FROM: STHR HAULING 11-IC January 3, 2007 Prime Construction Group, Inc. 1000 Jetstream Drive Orlando, FL 32824 TO: 407B5681.82 85681.02 Re: Cloud Branch Drainage Improvements. Attention: Katen Patel The haul rate of contaminated material from Lake Avenue & I P Street, Sanford, to the dumpsite in Kissimmee is $18.00 per ton. This price includes all necessary tolls. Should you require any further information, please do not hesitate to contact roe. Sincerely, ' a.. 4-a— r Mervyn Reece President F.D.O.T D.B.E. M.B.E. M.W.O.B.E. P.O.BOX 915437 WNCWOOD FLORIDA 32791 OFFICE (407) 6824345 FAX (407) 662 -4367 AN - .31 •-ddb f 11:14 F KUf I : 5. UHKF� Immri.n 'M r c2 r5 U40d IU:>K704078568182 P.2 F.D.O.T D.B.L KILL hLW.0.8.& P.O.803< 915437 L ONC;WOOD FLORIDA. 42791-5437 OFFICE (407) "24345 Fat (407) 612 -4367 SOLD TO: INVOICE NO.: 13530 PRIME CONSTRUCTION GROUP, INC. INVOICE DATE: 1/12/2007 P.O. BOX 590507 CONTAMINATED SOIL HAULING ORLANDO, FL 32859 -0507 BY THE TON LOCATION: DATE CLOUD BRANCH DRAINAGE IMPROVEMENTS —PHASE I ?ICFCET # TRUCK # UNITS PRICE PER UNIT AMOUNT 1/10/2007 26192 1 70.29 $18.000 $1,285.22 1/1012007 19787 7 76.64 $18.000 $1,379.52 1/10/2007 25201 101 71.66 $18.000 $1,289.88 1/10/2007 26505 301 73.19 $18.000 $1,317.42 1/10/2007 26977 702 70.95 $18.000 $1,277.28 1/10/2007 26169 2123 80.79 $18.000 $1,454.22 TOTAL: 443.53 $18.000 $7,983.54 1/11/2007 26183 1 47.8 $18.000 $860.40 1/11/2007 19768 7 48.04 $18.000 $864.72 1/11/2007 25270 101 45.38 $18.000 $816.84 1111 /2007 26508. 301 48.88 $18.000 $879.84 1/11/2007 26978 702 44.19 $18.000 $795.42 1/11/2007 28170 2123 51.33 $18.000 $923.94 TOTAL: 285.62 $18.000 $5,141.16 TOTAL: 729.15 TOTAL: $13,12470 DEC -15 -2006 08:38 FROM :HESS__ & FERRANTE 5042477003 loll TREATMENT 7ERVICE! ine. March 21st, 2006 TO ALL STS CUSTOMERS-.. ij :4078568182 P:4/4 As of April 3rd, 2006, the following prices on incinerationpetroleum contaminated soils will be as follows: Note: We do -not transport! 0•- 33 Tons (minimum tee) All over the above: 30 -days payment 45 -days payment 45 - 60 days payment $800.00 (30 -day pay) $23.00 /ton $24.00 /ton $26.00 /ton We cannot wait past 60 -days for payment on any-jobs. You will need to make financial arrangements with your bank etc .to see that we get.pai:d. within this time period, as we cannot .finance or carry any debts past this time limit. These prices may later be adjusted if fuel prices go up. On your billings you will be billed at the highest rate $26 /tn and the discount will be offered on the in (as per above) -{L We cannot take any clay or gumbo We can only take petroleum contaminated soils If trucks are lined with plastic there will be an additional charge of 4 $100 /per load If there is plastic all thru the dirt & alot of debris it will be an extra $50 /per load All pr -burn samples & soil site data sheet must be in our hands. at least 2 -days prior to the job starting just to make sure it is soils we can take. Craig Keene does all the scheduling of the soils that comes in. His cell phone number is 407- 973 -6037 if you have any questions please call us at the number listed below: f . Craig A Keene OE- ce Hours 7AM to 317m �° n thru Thvrsl - 'Z v r 7 to vl� Friday yo can call. Craig on his cell phone i f you need him 3505 PLIG MILL ROAD 0 KISSI FLORIDA 34741 -6462 * (407)9&3-8414 ® FAX(407)933-4521 �I 1 1� OIL TReRT eNT INVOICE NO. #27 -101 _=IERVICC-f ina. - PUG MILL ROAD KISSIMMEE, FLORIDA 34741 -6462 DATF- 1115/07 (407) 933 -8414 • FAX (407)P33 P.O.# 530-10 S ,Ytime Construction Group, Inc. Job: City of Sanford 0 P.O, Box 590507 Coastline Park L orl do, FL 32859 -0507 Poplar & e Street 0 Sanfat'd, FL T Attention. Patti Maus delvd: 1/10107.1/11/07 0 QUANTITY QF- $QRIPT {ON AMOUN 729.15 lTns Services for incineration of petroleum rantsrnhw d soils at $26.00 a ton An additional charge for: 2 pre -burn samles trash in loads TOTAL. Manifest #2725 -2733, 2735.2737, 2739 -2741, 2743 -2745, 2748, 2750 -2755, 2757, 2760, 2762 -2764 (copies en4osed) Note; A certificate of recycling will be issued after payment & when the post buns come back from the lab. 30-day payment $3 /ton discmmt. (2, 197,45) 2/14107 45 -day payment $2/ton discount (1, 458.30) 3/1/07 After 45 stays- no discount $18,957.90 $450.00 S100,00 $19, 507.90 INVOICE €/3:d 38tiSS?S8`Ob:01 200 "tr3i706 31NtU1 GJ 2 N0ISS3H :W0J3 2T :tT Z ®83- ST -NHr SECTION 00945 WORK DIRECTIVE CHANGE FORM Work Directive No.: 5 Name of Project: Cloud Branch Drainage Improvements - Ph. 1 (IFB 05/06 -08) Effective Date: Owner: City of Sanford Contractor: Prime Construction Group, Inc. Description of Change: Modify 5 x 5 box culvert and S -21 to accommodate existing gravity sewer between 13 St and 12 St, and replace 26 LF of existing 8" sanitary sewer with new 8" DI sewer. Reason for Change: Existing sewer lines were encountered while installing the 5x5 box culvert between 13 St and 12 St., and while enclosing the existing ditch between 13 St and 12 St. At the City's request the new box culvert and S -21 were modified and the sewer was changed from clay to ductile iron in the conflict areas. If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based thereon will involve one of the following methods of determining the effect of the change(s). Method of Determining the Change in Contract Price Method of Determining the Change in Contract Time Time and Materials X Unit Prices Cost Plus Fixed Fee Other Estimated increase ( �'a9Grea ) in Contract Price = $8,766.53 If the change involves an additional increase, estimated amount is not to be exceeded without further authorization. Contractor's Records Engineer's Records X As Specified Below Other Estimated increase ( d°GPeaS9) in Contract Time = 1 days. If the change involves an additional increase, estimated time is not to be exceeded without further authorization. 90945 -1 SPECLIB062703 Recommended B CPH Engineers, I c Date Executed Bv: er's Autho`riz,6d presentative Date 2 -7 -0"7 Contractor's A Pwzed Representative Date END OF SECTION SPECLIB062703 PRIME CONSTRUCTION GROUP, INC. cGCO37504 CUCO56650 QB33325 1000 Jetstream Drive, Orlando, FL 32824 407- 856 -8180 PH P.O. Box 590507, Orlando, FL 32859 -0507 (Mailing Address) 407- 856 -8182 FX January 3, 2007 CPH Engineers 500 West Fulton Street Sanford, FL 32771 Attn: Rocco Nasso, P.E. 530 -02 -010 RE: Cloud Branch Drainage Improvements — Phase I City of Sanford Project No.: 05/06 -08 Prime Construction Group, Inc. Job No. 530 CO Proposal — Modify 5x5 box culvert and S -21 to accommodate existing 8" sanitary sewer line between 13 & 12 Street Dear Rocco: Attached please find the Change Order Proposal to modify 5 x 5 box culvert and S -21 ditch bottom inlet and to replace 26 LF of existing 8" sanitary sewer with new 8" DI sewer between 13 and 12 Street. The above sewer line was not shown in the plans and encountered while laying the storm sewer and box culvert. This proposal includes all labor, material, equipment and subcontractor costs for the following: • Modify 5 x 5 box culvert and S -21 - $5,646.53 • Replace 8" sanitary sewer with new 8" DI sewer — Increase Pay Item # 144 quantity by 26 LF at $120.00 /LF - $3,120.00 The total value of the above proposal is valued at $8,766.53 and one (1) additional day. If you have any questions regarding the Change Order Proposal, please do not hesitate to call. Sincerely,:, OtaOlpatel Project Manager KPlpac F: \Project_ Management\Jobs \530 Cloud Branch Drainage Irnp. Phase 1\02Correspondence \To -from Engineer CPH\010 CO Proposal -Modify S- 21 and 50 BC.doc Change Order Proposal Change Request No.: 530 -06 Dat Owner Reference: Description: Modify 5x5 Box Culvert & S -21 to accommodate exist. 8" sanitary sewer line between 13th & 12th Street PCG Labor with Burden 1 Modify 5x5 box culvert and S -21 DBI Foreman, Pipe i 1 Days $489.00 $489.00 to accommodate existing 8' sanitary sewer line Pipe Layer 1 1 Days $336.00 $336.00 Pipe Tallman 1 1 Days $294.00 $294.00 Pipe Laborer 1 1 Days $273.00 $273.00 Operator, Track Excavator 1 1 Days $399.00 $399.00 Operator, Loader 1 1 Days $315.00 $315.00 $2,106.00 PCG Labor Subtotal PCG Labor Markup 15.0 $315.90 Materials Material Subtotal Material Tax 6.50% Material Markup 15.00 Equipment and Other Rentals Modify 5x5 box culvert and S -21 DBI Excavator, PC 300 1 Day $980.00 $980.00 to accommodate existing B' sanitary sewer line Pickup Truck & Cell Phone 1 Day $175.00 $175.00 Loader, JD 644 - 4 CY 1 Day $765.00 $765.00 Saw, Cutoff / Demolition 1 Day $60.00 $60.00 $1,980.00 Rental Subtotal Rental Tax 6.50% $128.70 Rental Markup 15.00% $316.31 Subcontracts 1 Concrete Cutting and Breaking - Saw cut 5 x 5 box culvert and 1 LS $570.00 $570.00 S -21 DBI Subcontractor Subtotal $570.00 Subcontractor Markup 5.00% $28.50 Change Order Subtotal $5.445.41 Daily Jotslle Overhead 1.00 Days $159.00 $159.00 Small Tool Allowance 2.00% $2,106.00 $42.12 $5,646.53 Bond Amount 2.00% Charge Order Subtotal $5,646.53 Pal Item A 144 Increase 25 LF $120.00 $3,120.00 Change Order Grandtotal $8.766.53 Aoanlonoi uonrracl Ilme re(lueareu This estimate Is valid for 30 days. F 1F,- 1/an.p«n.nNO Mud 8,- D--- . I e•,. , Concrete Cutting & Breaking Co. Phvsical Address: Remit Payments Only to: 4501 Airwest SE 1804 Reliable Parkway Grand Rapids, MI 49512 ,Chicago IL 60686 -0001 (616) 554 -4876 (616) 554 -5032 fax • Invoice No. WSHS32220 Date 11/30/2006 Customer ID PRIM- CON -OR PAGE 1 PRIME CONSTRUCTION GR U'—� (� p CLOUD BRANCH DRAINAGE IMPROVE P.O. BOX 590507 1 (-j 13TH & LAKE ORLANDO, FL 32859 -0507 U + SANFORD. FL DE C I r! _ Work Done:11 /15/2006 thru 11/15/2006 Our Locations Delray Beach, FL 561- 278 -2700 Grand Rapids, MI Service 616- 451 -2886 Brecksville, OH 440- 546 -0500 Orlando, FL 407- 423 -3366 Grand Rapids, MI Highway 616 -456 -9441 Columbus, OH 614- 257 -1827 aCKsonvi e, L - TOUT- - =171985 PAishawaka, IN 574- 255 -8805 Lancaster, NY . 716- 684 -0262 Raleigh, NC 919- 779 -7344 Okemos, MI 517 - 381 -0222 Albany, NY 518 -862 -0070 • • 530 ��TITY DESCRIPTION UNITPRICE EXT. PRICE 2.00 12'X 39" X 8" CONCRETE WALL ROUGH OPENINGS WITH HYDRAULIC 185.00 370.00 HAND SAW 1.00 98" X 25'X 6" CONCRETE WALL ROUGH OPENING WITH 200.00 200.00 HYDRAULIC HAND SAW /4 Sn S QL J - 2-4 �..:.;C Sales Total 570.00 Terms: Net 30 Days. Any invoices over 45 days are subject to a finance charge Of 1.5% (I8% atmual) as well as collection costs. We Gladly Accept Mastercard, Visa, Amex & Discover Thank you for your Business Please Pay from Invoice No Statement will be issued Shipping 8 Handling 0.00 Misc. Charges 0.00 Tax Total 0 00 570.00 Less Paid Amount 0.00 _Please PayDMIC0Td?AL �3• SECTION 00945 Work Directive No.: Name of Project: Effective Date: Owner: Contractor: WORK DIRECTIVE CHANGE FORM 0 Cloud Branch Drainage Improvements - Ph. 1 (IFB 05/06 -08) City of Sanford Prime Construction Group, Inc. Description of Change: Modify 3 x 8 box culvert and install 12" PVC storm sewer at 20 Street ditch crossing Reason for Change: Existing 12" storm sewer was encountered while installing the new 3 x 8 Box Culvert across 20 Street (this storm sewer was previously unknown). A portion of the existing storm pipe will be removed and new 12" PVC storm sewer installed and connected to the new box culvert. If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based thereon will involve one of the following methods of determining the effect of the change(s). Method of Determining the Change in Contract Price Time and Materials X Unit Prices Cost Plus Fixed Fee Other Estimated increase ( d°a�ease ) in Contract Price = $5,352.46 If the change involves an additional increase, estimated amount is not to be exceeded without further authorization. Method of Determining the Change in Contract Time Contractor's Records Engineer's Records X As Specified Below Other Estimated increase (de e) in Contract Time = 1 days. If the change involves an additional increase, estimated time is not to be exceeded without further authorization. 00945 -1 SPECUB062703 Rec�°mmended By: ul— C"PH Engineers, In Executed By: Owner's resentative Date 7— - Z _ ZC� Date Contractor's Authgk Representative END OF SECTION Date 00945-2 SPECUB062703 PRIME CONSTRUCTION G INC CGCO37504 CUCO56650 Q933325 1000 Jetstream Drive, Orlando, FL 32824 407 -856 -8180 PH P.O. Box 590507, Orlando, FL 32859 -0507 (Mailing Address) 407 - 856 -8182 FX January 4, 2007 CPH Engineers 500 West Fulton Street Sanford, FL 32771 Attn: Rocco Nasso, P.E. 530 -02 -012 RE: Cloud Branch Drainage Improvements — Phase I City of Sanford Project No.: 05/06 -08 Prime Construction Group, Inc. Job No. 530 CO Proposal — Modify 3x8 box culvert and Install 12" PVC storm on 20 St. Dear Rocco: Attached please find the Change Order Proposal to modify 3 x 8 box culvert to accommodate new 12" PVC storm on 20 Street. The above 12" storm drain replaced existing 12" concrete pipe not shown in the plans and encountered while laying the box culvert across 20 Street. This proposal includes all labor, material, equipment and subcontractor costs for the following: Remove existing 12" concrete pipe Install new 12" PVC pipe Modify 3 x 8 box culvert to accommodate the above pipe The total value of the above proposal is valued at $5,352.46 and one (1) additional day. If you have any questions regarding the Change Order Proposal, please do not hesitate to call. Sincerely,.. O a n Ktel Project Manager KP /pac P: \Pmiext_ManagementVobs'.530 Cloud Branch Drainage hop. Phase I \02Coarespondence \To -from Engineer CPHV2 CO Proposal - Modify 3x8 BC & Install 12 PVC Stonn.doc Change Request No.: Owner Reference: Description: Change Order Proposal 530-08 Modify 3x8 BC on 20th St & install new 12" PVC Storm Drain Date: 4- Jan -07 Addltlonai Contract i ime mquesteo This estimate Is valid for 30 days. F1Pois<1 Me.upn�Nob C.b�a amen ro.M.p 0 a� PCG Labor with Burden 1 Remove existing 12" concrete pipe in conflict with 3x8 BC and Foreman, Pipe 1 1 Days $489.00 $489.00 install new 12' PVC pipe on 20th Street Pipe Layer t 1 Days $336.00 $336.00 Pipe Tailman 1 1 Days $294.00 $294.00 Pipe Laborer 1 1 Days $273.00 $273.00 Operator, Track Excavator i 1 Days $399.00 $399.00 Operator, Loader i 1 Days $315.00 $315.00 $2,106.00 PCG Labor Subtotal PCG Labor Markup 15.00% $315.90 Materials 1 12" Flex Sewer Coupling 2 EA $39.96 $79.92 1 12" SCH40 PVC Pipe 40 LF $14.00 $560.00 $639.92 Material Subtotal Material Tax 6.50% $41.59 Material Markup 15.00% $102.23 Equipment and Other Rentals 1 Remove existing 12' concrete pipe in conflict with 3x8 BC and Excavator, PC 40 1 Day $280.00 $280.00 install new 12' PVC pipe on 20th Street Loader, JD 644 - 4 CY 1 Day $765.00 $765.00 Pickup Truck & Cell Phone 1 Day $175.00 $175.00 $1,220.00 Rental Subtotal Rental Tax 6.50% $ 79.30 Rental Markup 15.00% $194.90 Subcontracts Concrete Cutting and Breaking 2 EA $215. DO $430.00 1 18" Dia Core in 3x8 Box Culvert for 12' PVC Pipe on 20th $430.00 Subcontractor Subtotal Subcontractor Markup 5.00% $21.50 Change Order Subtotal $5.151.34 Daily Jobsde Overhead 1.00 Days $159.00 $159 00 Small Tool Allowance 2.00°/ $2,106.00 $42.12 $5.'52 46 Pond Amount 2.00% Change Order Subtotal $6.362.46 Addltlonai Contract i ime mquesteo This estimate Is valid for 30 days. F1Pois<1 Me.upn�Nob C.b�a amen ro.M.p 0 a� 6ec, 2 ?. 2006 11 :31AM? CONC CUT & BRO CO, bib 554 5032 Concrete Cutting & Breaking Co. Phvsical Address! Remit Payments Only to: 4501 Airwest SE I804 Reliable Parkway Grand Rapids, MI 49512 Chicago IL 60686 -0001 (616) 554 -4876 (616) 554 -5032 fax No. o40 P Invoke No. CDME30132 Date 12/27/2006 Customer ID PRIM- CON-OR PAGE 1 PRIME CONSTRUCTION GROUP, INC. P.O. BOX 590507 ORLANDO, FL 32859 -0507 CLOUD BRANCH DRAINAGE IMPRO 137H & LAKE SANFORD.FL Work Done: 12/12/2006 thru 12/12/2006 O ur Locations Delray Beach, FL 561. 278 -2700 Grand Rapids, MI Service 616 -451 -2886 Brecksville, OH 440 - 546-0500 Orlando, .FL 407.423 -3366 Grand Rapids, M! Highway 516456.9441 Columbus, OH 614-257-1827 - Mishawaka, IN 574-255.8805 Lancaster, NY 716.664 -0262 aacsonvi e, Raleigh, NC 919- 779 -7344 Oksmos, MI 517- 381 -0222 Albany, NY 518.862.0070 1,00 24" DIAMETER CORE 12" DEEP - CONCRETE WALT. (11TH ST) OA rri'J - g/rv-t yhP-' 435.00 435 -00 2.00 18" DIAMETER CORES 8" DEEP • CONCRETE WALL (20TH ST) _ 6 -A%rr. Ir "AcP 215.00 430.00 1.00 24^ X 12" ROUGH OPENING WITH HAND SAW X 5" CONCRETE BOX — f_ 31 125.00 125.00 STRUCTURE Terms: Net 30 Days. Any invoices over 45 days are subject to a finance charge of 1.5% (18 annual) as well as collection costs. We Gladly Accept iwlastercard, i5a, Timex & Discover Thank you for your Business Please Pay from Invoice No Statement will be issued i ! 990.00 Salas Total Shipping 8 Handling D.00 MO. Char966 0.00 Tax Total 0.00 990.D0 Lem Paid Amount 0.00 990,00 21;12609 PRINIE CON REMIT TO MAINLINE SUPPLY - ORLANDO WACHOVIA BANK PO BOX 934450 ATLANTA, GA 31193 -4538 JVLII IV PRIME CONSTRUCTION GROUP INC P.O. BOX 590507 ORLANDO, FL 32859 r� MAINLINE SUPPLY - ORLANDO 2291 W AIRPORT BLVD SANFORD, FL 32771 Telephone: 407- 688 -9191 ustomer NicKup - BRANCH NO .iNV010E "DATE ORDER NO — SHIPPING METHOD CUSTOMER NO TERMS = JOB NAME JOB NO SLS DUE DATE SHIP DATE FER10021212 12" FLEX SEWER CPLG CLAYXPVC EA 2 39.960 79.92 Payment of Due On If Paid By You Owe 2132609 85.52 1/10/07 12/11/06 E5.52 . .. NO RETURNS ACCEPTED WITHOUT AMOUNT DUE 1 7 _ 9 . 92 PRIOR AUTHORIZATION c ALL CLAIMS FOR DAMAGE. MUST BE FILED j `� . 1 13 0 WITH CARRIER. F 00 ALL SALES ARE SUBJECT TO THE TERMS AND CONDITIONS OF SALE TOTAL DUE AS F,2 ON THE REVERSE SIDE. Pg 1 INVOICE - '! ' ` ., jf _ ?129%9;- 1 RFWiT Tff WACHOVIA BANK PO BOX 934450 ATLANTA, GA 31193 -4538 PRIME CONSTRUCTION GROUP INC P.O. BOX 590507 ORLANDO, FL 32859 MAINLINE SUPPLY - ORLANDO 2291 W AIRPORT BLVD SANFORD, FL 32771 Telephone: 407- 688 -9191 16th. Street Sanford, FL 32771 BRANCH Nd - INVOICE DATE- - -- ORDER - NO - SHIPPING METHOD - CUSTOMER NO TERMS -- - PO NO JOB NAME JOB NO SL5 DUE DATE 5111PDATE 1 1 1 1 i'� 1 1 � 1� 1 1 1• Pg 1 INVOICC ! " IUR AU HUNIZAT1(IN ` �, :• . �v 1 ALL CLAIMS FOR DAMAGE MUST BE FILED TAX _ 'A/17H CARRIER 31 60 ALL SALES ARE SUBJECT TO THE - . FREIGHT TERMS AND CONDITIONS OF SALE � TOTAL DUE 593.60 ON THE REVERSE SIDE. SECTION 00945 Work Directive No.: Name of Project: Effective Date: Owner: Contractor: WORK DIRECTIVE CHANGE FORM 7 Cloud Branch Drainage Improvements - Ph. 1 (IFB 05/06 -08) City of Sanford Prime Construction Group, Inc. Description of Change: Modify 3 x 9 box culvert to accommodate existing gravity sewer along 16 St, and replace 40 LF of existing 8" sanitary sewer with new 8" DI sewer. Reason, for Change: Existing sewer line was encountered while installing the 3x9 box culvert along 16' St. At the City's request, the new box culvert was modified and the sewer was changed from clay to ductile iron in the conflict areas. If a claim is made that the above change(s) have affected Contract Price or Contract Time, any claim for a Change Order based thereon will involve one of the following methods of determining the effect of the change(s). Method of Determining the Change in Contract Price Time and Materials X Unit Prices Cost Plus Fixed Fee Other Estimated increase ( e ) . in Contract Price = $11,003.67 If the change involves . an additional increase, estimated amount is not to be exceeded without further authorization. Recommended By: CPH Engineers, Inc. Method of Determining the Change in Contract Time Contractor's Records Engineer's Records X As Specified Below Other Estimated increase (decd in Contract Time = 1 days. If the change involves an additional increase, estimated time is not to be exceeded without further authorization. �F Date 00945 -1 SPECLIB062703 Executed By: Representative END OF SECTION ,? -z?- E Date H - 3- o-) Date 00945 -2 SPECLIB062703 PRIME CONSTR CTION GROUP, INC. C G I CO37504 CUCO56650 QB33325 1000 Jetstream Drive, Orlando, FL 32824 407- 856 -8180 PH P.O. Box 590507, Orlando, FL 32859 -0507 (Mailing Address) 407- 856 -8182 FX March 12, 2007 CPH Engineers 500 West Fulton Street Sanford, FL 32771 Attn: Rocco Nasso, P.E. Lu�.. 1. I 530 -02 -014 RE: Cloud Branch Drainage Improvements —Phase I City of Sanford Project No.: 05/06 -08 Prime Construction Group, Inc. Job No. 530 CO Proposal — Modify 3x9 box culvert and replace 8" sanitary sewer on 16 St. Dear Rocco: Attached please find the Change Order Proposal to modify 3 x 9 box culvert to accommodate existing 8" sanitary sewer line on 16 Street. The above 8" sewer line was not shown in the plans as conflict and was encountered while laying the box culvert across 16 Street. This proposal includes all labor, material, equipment and subcontractor costs for the following: • Modify 3 x 9 box culvert to accommodate the 8" sewer line • Replace 8" sanitary sewer with new 8" DI sewer — Increase Pay Item # 144 quantity by 40 LF at $120.00 /LF - $4,800.00 The total value of the above proposal is valued at $11,003.67 and one (1) additional day: If you have any questions regarding the Change Order Proposal, please do not hesitate to call. Sincerely, v Ketan Patel Project Manager KP /pac F'. `Project ManagementJohs'530 Cloud Bra tic it Drainage Inip. Phase 1`,02Conespondenee'�To -From Engineer CPH,014 CO Proposal -Modify 3x9 BC & Reroute 8 inch San Sewer at loth St.doc Change Order Proposal j l Change Request No.: 530 -09 Date: 12- Mar -07 Owner Reference: Description: Modify 3x9 Box Culvert Replace 8" Sanitary Sewer on 16th St. Crew Size Quantitv Unit Unit Price Extension PCG Labor with Burden 1 Modify 3 x 9 Box Culvert on 16th St. to accommodate existing Foreman, Pipe 1 1 Days $489.00 $48900 8' sanitary sewer line Pipe Layer 1 1 Days $336.00 $336.00 Pipe Tailman 1 1 Days $294.00 $294.00 Pipe Laborer 1 1 Days $273.00 $273.00 Operator, Track Excavator 1 1 Days $399.00 $399.00 Operator, Loader 1 1 Days $315.00 $315.00 )CG Labor Subtotal $2,106.00 PCG Labor Markup 15.00% $315.90 Materials 1 Concrete - Poured invert on 3 x 9 Box Culvert at the conflict 1 LS $467.75 $467.75 3 CY with minimum load charge Aaterial Subtotal $467.75 Material Tax 6.50% $30.40 Material Markup 15.00% $74.72 Equipment and Other Rentals Modify 3 x 9 Box Culvert on 16th St. to accommodate existing Excavator, PC 300 1 Day $980.00 $980.00 8" sanitary sewer line Pickup Truck & Cell Phone 1 Day $175.00 $175.00 Loader, JD 644 - 4 CY 1 Day $765.00 $765.00 tented Subtotal $1,920.00 Rental Tax 6.50% $124.80 Rental Markup .15.00% $306.72 Subcontracts 1 Concrete Cutting and Breaking - Saw Cut 3x9 Box Culvert 25 LF $25.00 $625.00 ubcontractor Subtotal $625.00 Subcontractor Markup 5.00% $3125 Change Order Subtotal $6,002.55 Daily Jobsite Overhead 1.00 Days $159.00 $159.00 Small Tool Allowance 2.00% $2,106.00 $42.12 $6,20367 Bond Amount Chance Order Subtotal $6.203.67 - - -- - = 40 ! F $' O DO $4,800 0G � d y� Glc el Gr it :iiocei $11,003.67 yditional Contract Time requested 1 Day `Os estimate is valid for 30 days. :P'.'- Mana -- J.- 5501 -11 6-111 i- imp. Pk.... K06C- M ..... m -%C' a , 0.aars Proposal 9 M.0, 3.9 SC a' 8-1. San Sarni C-f.l 16p 5+ XL �11"Pul Dal. Rinker Materials 3626 Quadrangle Blvd Ste 200 • Orlando, r-L 32817-8348 0 -a PRIME CONSTRUCTION GRO1UP INC 41- PO BOX 590507 C:3 m C3 ORLANDO, FL 32859-0507 C. c ( C. N (o CC) c\1 0 CY) 0 Lo Lr) ( 5 o c)) 0 c\j w 0 cy) 0-0 6 Z to O O aQ. 0 0 0 c) - 0 0 o Ls 0000 0 ti 0 CV CV Ln M o (D Lo U) U'> c\1 ce) 0000 x cts Lo O 0 m 0 CC L) 0 C-) L) 0 CL >- a- (L LL — — — +— Z V) 0 0 0 Lf) 0 0 0 1- N LL O O cr) (L >- EL CL 0 0 0 0 0000 Coco 1-• CY) ,-: 1: 70 Lij (D Lu rr 0 cc a: 0 < L) LL T Lu z U -j < (D 0 a U) < z < 0 0 LLJ T -j Cc: 0 M 2L) z ::) q 0 LLJ 0 U) 1-2 ir C[ 0 5 8 Lu Z Z) C Lu LL co 0 (3) co CD (D 00 IT — �2 m r- c? Lo c\1 t-- t- ii O l t .0 > 0 Lo 4. Z E i; AFB 0 Lo O 7 CY) V U LU — — — — .0 > 0 Lo 4. Z E i; AFB 0 Lo O 7 CY) V U LU — — — — U) L r) U) 'o m N 1� kn C\J 0) 0) 0) CY) >- N IN IN "A 00 00 co OD CL 0 (m r- (D 7r 0 0 0 c) 0 II < CL cr) 0 c) co co n C6 7 uj E c m m a = 0 CD M Z c\4 c\f n c) co c) X Ln ul Lo Lo C11 c\1 N N V O C S j Z c) c) r) co 0 (D 0 0 co co co 00 ci � � PV n Concrete Cutting ic�i i $r�alcincgrCp,' G ;( Iii;. i ® Phvsical Address: -- Rernit-Pitvments 0niy - to: ---- -' 4501 Airwest SE 1804 Reliable Parkway Grand Rapids, MI 49512 Chicago IL 60686 -0001 (616) 554 -4876 (616) 554 -5032 fax • Invoice No. WSSV30147 Date 2/22/2007 Customer ID PRIM- CON -OR PAGE 1 PRIME CONSTRUCTION GROUP, INC. 16TH STREET & LAKE AVENUE P.O. BOX 590507' CLOUD BRANCH ORLANDO, FL 32859 -0507 SANFORD, FL Work Done:2/12/2007 tliru 2/15/2007 Our Lo cations Delray Beach, FL 561 -278 -2700 Grand Rapids, MI Service 616 - 451 -2886 Brecksville, CH 440- 546 -0500 Orlando, FL 407- 423 -3366 Grand Rapids MI Highway 616 - 456 - 9441 Columbus, OH 614 -257 -1827 araso FL 'I- 5S6'0A4 Mishawaka. IN 574 -255 -8805 Lancaster,. NY 716 -684 -0262 Jacksonville, FL 904 - 262 -9985 Okemos, 101 517 - 381 -0222 Albany, NY 518- 862 -0070 CUSTOMER P.O. NO. • CCBJob Number ' •'' QUANTITY . DESCRIPTIDN UNIT PRICE EXT. PRICE • tl • • D 00 1 ZS F - Pic. (�(i21��> 2 T FT c%-c 7 � 21 I RET /DATE:$ hr= 1'RL4fPtf j G�. � t �w�vR !,: REF d — — Terms: Net 30 Days. Any invoices over 45 days are subject to a finance charge of 1.5% (18% annual) as well as collection costs. We Gladly Accept ?a t °rc: °:.i, Vi-a, Amex ,& Discover Thank you for your Business Please Pay from Invoice No Statement will be issued Sales Total 1,250.00 Shipping & Handling . 0.00 Misc. Charges 0.00 Tax Total 0.00 1,250.00 Less Paid Amount 0.00 - _,,PleasePayInvalr — TDTAt : ee r N 215 K Tait Vineland rd., Orlando. FL 3202+ Phone 407 - 856 -0997 Fax 407- 856 -0798 FL CGC- 061534 t . "I n t Jo Ticket # Jobsite Address :ontractor Date 1 � — )'� Start Time � Employee Name " _ ,ontract Phone # Job Description , tuantity Description of • t LW r� i • • Related Standb explanation• I;Fr= tP.4�'tttc total hours: ; WE SU�v1E NO PONSIBILITY FOR LAYOUT OR D' IMAGE O t UTILITIES E ` CC &B la: natjAe �° Contractor Signature ,� �� Job# P.O.# 1211- 1- 1211., , n.,* A—i". _1nh I Cinch Deoart Job Shoo In Shop Out Total Hours Operator notes including blade information: Contractor notes: G � t Operator notes including blade information: Contractor notes: