1012-Gibbs & Register Change OrderSECTION 00950 CHANGE ORDER FORM Change Order No. 3 (FINAL) Project Title CR 46A / Airport Boulevard Utility Relocatic Bid No. IFB 05/06 -24 Owner: City of Sanford Contractor: Gibbs and Register, Inc. Agreement Date: December 14, 2006 t r p This Change Order is necessary to cover changes in the work to be performed under this Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS apply to and govern all work under this Change Order. THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS: (1) Original Contract Price (2) Current Contract Price (Adjusted by Previous Change Orders) (3) Total Proposed Change in Contract Price (4) New Contract Price (Item 2 + Item 3) (5) Original Contract Time (6) Current Contract Time (Adjusted by Previous Change Orders) (7) Total Proposed Change in Contract Time (8) New Contract Time (Item 6 + Item 7) (9) Original Contract Substantial Completion Date (10) New Contract Substantial Completion Date 00950 -1 $ 329,000.00 $ 407,253.85 $ 13,705.07 $ 420,958.92 240 Days 317 Days 45 Days 362 Days February 16, 2008 March 17, 2008 SPECLIB120902 k CHANGES ORDERED lid #LK Description of Change: Quantity Adjustments Reason for Change: Incorporate actual constructed quantities into the contract Change in Contract Price: ($5,027.70) Change in Contract Time: 0 Days ITEM 2 Description of Change: Relocation of approximately 25 LF +1- of existing 10" water main along Airport Blvd at Country Club Rd including the removal of approximately 25 LF of existing 10" water main. (see attached sketch) Reason for Change: The County's proposed construction at Country Club Road and Airport Blvd conflicts with the City of Sanford's existing 10" water main at structure B -102 Change in Contract Price: $18,732.77 Change in Contract Time: 45 Days CHANGE ORDER SUMMARY No Description Change in Contract Price Change in Contract Time 1 Quantity Adjustments ($5,027.70) 0 Days 2 Relocation of 10" WM at Airport Blvd. & Country Club $18,732.77 45 Daxjq TOTAL $13,705.07 45 Days WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly and indirectly from the change. Acceptance of this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change 00950 -2 SPECLI6720902 Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change Order. APPROVAL AND CHANGE ORDER AUTHORIZATION ACKNOWLEDGMENTS The aforementioned change, and work affected thereby, is subject to all provisions of the original Agreement and specifically changed by this Change Order; and It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original Agreement other than matters expressly provided herein. ATTEST: L A - _ ( retary) i 1 to Date (Corporate Seal) ATTEST: ignature) Gibbs and Register Inc. Contractor Printe Name nd Title of Officer (Signature) 1/0l Date City of Sanford O er C PrintVAame and Ti Date By (Signature) (Seal) Date END OF SECTION 00950 -3 SPECU8120902 CITY OF SANFORD C.R. 46A - AIRPORT BLVD UTILITY RELOCATIONS (IFB 05/06 -24) CHANGE ORDER NO. 3 (FINAL) - ATTACHMENT MW 4- n"ANTITY ADJU- STMENTS DESCRIPTION UNITS QUANTITY UNIT COST TOTAL COS Seed and Mulch SY - 3617.8 $1.00 $3,617.80) Sodding (Bahia) SY - 1385.3 $3.00 ($4,155.90) Remove and Replace Concrete Curb and Gutter LF -15 $80.00 ($1,200.00) Remove and Replace Asphalt Pavement and Base SY -31.5 $80.00 ($2,520.00) 24" D. I. Wafer Main LF 5 $190.00 $950.00 Remove Existing 6" Force Main LF 240 $9.50 $2,280.00 Remove Existing 12" Force Main LF 228 $12.00 $2,736.00 Remove Existing 24" Water Main LF 25 $20.00 $500.00 TOTAL ITEM 2 - RELOCATE 10" WATER MAIN AT AIRPORT BLVD & COUNTRY CLUB RD taa,ucr. r u) DESCRIPTION I UNITS I QUANTITY UNIT COSTI TOTAL COST 10" Water Main relocation LS 1.00 $18,732.77 $18,732.77 TOTAL CHANGE ORDER SUMMARY Item 1 ($5,027.70) Item 2 $18,732.77 TOTAL $13,705.07 Original Contract Amount $329,000.00 C.O. No. 1 $34,549.49 C.O. No. 2 $43,704.36 Proposed C.O. No. 3 $13,705.07 Proposed New Contract Amount $420,958.92 ,78,!32.! / CITY OF SANFORD C.R. 46A - AIRPORT BLVD UTILITY RELOCATIONS (IFB 05/06 -24) CHANGE ORDER NO. 3 - ATTACHMENT TIME SUMMARY TIME CHANGE ITEM 1- QUANTITY ADJUSTMENTS 0 Da s ITEM 2 - RELOCATE 10" WATER MAIN AT AIRPORT BLVD & COUNTRY CLUB RD 45 Days TOTAL 45 Days CONTRACT TIME SUMMARY Contract Time Proposed Change Order No. 3 Change in Contract Time New Contract Time Date of Notice to Proceed Total Adjusted Contract Time Revised Substantial Completion Date Contract Time From Substantial Completion to Final Completion Revised Final Completion Date 317 Days 45 Days 362 Days 2/19/2007 362 Days 2/16/2008 30 Days 3/17/2008 JAN -11- 2008 02 From: To:4073300639 Paee:215 GIBBS & REGISTER, INC. 232 youth Dillard Street Winter Cirrden, Florida 34787 Telephone: (407) 654.6133 Facaittiile- (407) 6546134 January 10, 2008 Rnceo R. Nasso, P.E. CPH Engineers, Inc. 500 West Niton Street Sanford, Florida 32771 Re: CR46A /Airport Boulevard Uiilily Rclocations (1FI3 05/06 -24) Suhjecl: Airport Blvd. WM Relocation Change Order Dear Mr. Nx«.r The purpose of this letter it for provitic you with the Airport Blvd. 10" WAtcr main relocation change order proposal for the work JL , ,uribcd in your attached sketch(s). G &R is proposing to complete this work ti.r the tidal amount of $18,732.77. This work would be cumpleted under a single lane cln -iurc (M -F, 8:O0 a.m. to S:UO p.m.). G &R will hatch the roadway with asphalt millings and have the road opened at the completion of each work .hilt. Please provide us with Written ditection if you Wuuld like for us to proceed with this work. If you have any questions, or require additional infornnetiun, fccl free to) give me a call. Yours truly, / ue STF.R, INC. r Enclosures JADi -11 -2000 02:25 From: 01/10/.008 14:11 71N15A -06 AIRPORT 10" WATEI( l(ELULA11014 • • • PROJEC'I' MANA(OIRJ BID TOTALS Didilem Descliptiou 5 GENERAL CONmio NS 6 MAINTENANCE OF TRAFFIC 7 CI .FA RI NG/PREPARATION 10 10" WAIL'R I)LI 7 LE(MON To :4073300639 Paee:3'5 () Ilankity vRjq Vail Prirr Ri IA00 LS 4,943 .23 4,943.23 1.000 LS 4.655.66 4,655.66 1.rm 1 S 2,376.64 2,376.64 28 000 LIi 241.33 t,,757.24 Bid Total = _______> SIR,71177 JAN -11- 2008 02:25 From: To:4073300639 Paee:4 JOS NAME, Hy JOB NO: _ _ _. _ .__ CHECNEDBY Qal f 6HF L I NU.' WTE SCALE � 3 . s3 T.e .f v.+., ^:_- -3w ce•.C..IE 7 Air. 01l.U.. v " rl .i.i/� Imo:.. �r . S {•rr�a,�., • pj IJ+1 - Ti,. pw.y GP .f w.�., o%,n. • 34.5b - I / JAN-11-2008 02:25 From: Mgz CL i77Y S` To:4073300639 Y Vk v x'11 �\ �� c ' ;k ' � ��� ANI ION T fi�ii� �' cc:l:earraemn4nsca�. MIS ! ®I