1251 CFE Change OrderSECTION 00950
CHANGE ORDER FORM
Change Order No. 1
Project Title 1 ST Street Improvements Phase 2
Bid No. IFB 07/08 -21
Owner: City Of Sanford
Contractor: CFE Corporation
Agreement Date: December 11, 2008
Y:
1-s'?
IN
`'
6
This Change Order is necessary to cover changes in the work to be
performed under this Agreement. The GENERAL CONDITIONS,
SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS
apply to and govern all work under this Change Order.
THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS:
(1) Original Contract Price
(2) Current Contract Price (Adjusted by Previous Change Orders)
(3) Total Proposed Change in Contract Price
(4) New Contract Price (Item 2 + Item 3)
(5) Original Contract Time
(6) Current Contract Time (Adjusted by Previous Change Orders)
(7) Total Proposed Change in Contract Time
(8) New Contract Time (Item 6 + Item 7)
(9) Original Contract Substantial Completion Date
(10) New Contract Substantial Completion Date
00950 -1
$1,917,898
$1,917,898
$51,953.34
$1,969,851.34
165 Days
165 Days
13 Days
178 Days
June 19, 2009
July 2, 2009
SPECLIB120902
CHANGES ORDERED
ITEM 1
Description of Change: Moving Irrigation Controller
Reason for Change: Make the controller more accessible
Change in Contract Price: $1,309.85
Change in Contract Time: None
ITEM 2 Item
Description of Change: Variable Message Boards
Reason for Change: To Inform the Public all Businesses are Open
Change in Contract Price: $12,403.16
Change in Contract Time: None
ITEM 3
Description of Change: Add remove 3" abandon gas main at the same price as U -7
Reason for Change: Line is in the sub -grade
Change in Contract Price: $6,570.00
Change in Contract Time: 7 Days
ITEM 4
Description of Change: Move and replace existing light pole at STA. #11 +00
Reason for Change: Pole is in the way of wall construction
Change in Contract Price: $1,225.61
Change in Contract Time: None
00950 -2
SPECLIB120902
ITEM 5
Description of Change: Add 2 Connect Existing Sewer to New Manhole
Reason for Change: Cutting in Manholes (S -3) And (S -6) Originally called for only 2
Change in Contract Price: $ 2060.00
Change in Contract Time: 2 Days
ITEM 6
Description of Change: Install 1300' of 2" Sch. 40 PVC for future use electrical conduits
Reason for Change: Per Sam Samari
Change in Contract Price: $ 9,792.20
Change in Contract Time: 3 Days
ITEM 7
Description of Change: Encase Exxon sign in brick
Reason for Change: To make the sign match the wall
Change in Contract Price: $10,222.78
Change in Contract Time: None
ITEM 8
Description of Change: Modify existing Exxon Sign
Reason for Change: To make the sign accessible
Change in Contract Price: $1,225.61
Change in Contract Time: None
Item 9
Description of Change: Tie existing roof drain in to S -5
Reason for Change: Roof Drain already existed and was tied to an inlet
00950 -3
SPECLIBI20902
Change in Contract Price: $1,299.74
Change in Contract Time: None
Item 10
Description of Change: Install drain on south side of wall
Reason for Change: To get water out of Exxon parking area
Change in Contract Price: $2,948.14
Change in Contract Time: 1 Day
Item 11
Description of Change: Increase unit price on white brick by $0.20 per sf.
Reason for Change: Plan originally called for grey brick
Change in Contract Price: $253.76
Change in Contract Time: None
Item 12
Description of Change: Upgrade circuit homerun panel
Reason for Change: Original plan did not show a 2 side panel
Change in Contract Price: $3,719.10
Change in Contract Time: None
Item 13
Description of Change: Change CVS Driveway from Asphalt to Concrete
Reason for Change: To Make Everything on the Project Uniform
Change in Contract Price: $1,041.00
Change in Contract Time: None
00950 -4
SPECLIB120902
Item 14
Description of Change: Reduce North and South Wall 1 panel and 1 column each
Reason for Change: Right of way issues
Change in Contract Price: ($5,291.88)
Change in Contract Time: None
ITEM 15
Description of Change: Quantity Adjustments
Reason for Change: Incorporate actual constructed quantities into the contract
(See Attached)
Change in Contract Price: $3,174.27
Change in Contract Time: 0 Days
CHANGE ORDER SUMMARY
No.
Description
Change in
Contract Price
Change in
Contract Time
1
Moving Irrigation Controller
$1,309.85
0 Days
2
Variable Message Boards
$12,403.16
0 Days
3
Remove abandon gas line
$6,570.00
7 Days
4
Remove and replace existing light pole
$1,225.61
ODa s
5
Add 2 Connect to Existing Manhole S -3and S -6)
$2,060.00
2 Days
6
Install 1300' of future use conduit
$9,792.20
3 Days
7
Brick Around Exxon Sign
$10,222.78
ODays
8
Modify Exxon Sign
$1,225.61
0 Days
9
Tie existing roof drain into S -5
$1,299.74
0 Days
10
Install drain in Exxon parking lot
$2,948.14
1 Da
11
Change from Grey brick to White brick
$253.76
0 Days
12
Upgrade circuit homerun panel
$3,719.10
0 Days
13
Change CVS driveway from asphalt to concrete
$1,041.00
0 Days
14
Reduce North and South wall 1column and panel
$5,291.88
0 Da vs
15
Quantity Adjustments
$3,174.27
0 Days
Total
$51,953.34
13 Days
00950 -5
SPECLIBI20902
WAIVER This Change Order constitutes full and mutual accord and satisfaction for the
adjustment of the Contract Price and Contract Time as a result of increases or decreases in
cost and time of performance caused directly and indirectly from the change. Acceptance of
this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change
Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall
waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution
of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction
that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change
Order.
APPROVAL AND CHANGE ORDER AUTHORIZATION
ACKNOWLEDGMENTS
The aforementioned change, and work affected thereby, is subject to all provisions of the
original Agreement and specifically changed by this Change Order; and It is expressly
understood and agreed that the approval of the Change Order shall have no effect on the
original Agreement other than matters expressly provided herein.
ATTEST
(Secretary)
9 -20 --
Date
(Corporate Seal)
ATTEST:
ft -
/ ,
Date
(Seal)
` Contractor
Printe ame and Title of Offi er
B ignature)
8 -.co -o q
Date
City of Sanford
Owner
Tom George Interim City Manager
Printed Name and Title
�C
By ( ature)
August 24 2009
Date
END OF SECTION
00950 -1