1604* SE Cline Construction IFB 12/13-18 I ita°
•
r, • j Thursday, January 09, 2014 ; ;a
—1877-9
PURCHASING DEPARTMENT
TRANSMITTAL MEMORANDUM
To: City Clerk-
RE: SE Cline Construction Inc. IFB 12/13-18 Public Doc Facility @ Sanford
Marina
The item(s) noted below is/are attached and forwarded to your office for the following action(s):
Development Order Mayor's signature
Final Plat(original mylars) Recording
Letter of Credit I I Rendering
Maintenance Bond ® Safe keeping (Vault)
Ordinance Deputy City Manager
Performance Bond Payment Bond
Resolution City Manager Signature
City Clerk Attest/Signature
Once completed, please:
❑ Return originals to Purchasing
n Return copies
fl
Special Instructions:
Safe keeping...
From Date
T:\Dept_forms\City Clerk Transmittal Memo-2009.doc
SECTION 00627
CERTIFICATE OF FINAL COMPLETION
Project Title: Public Dock Facility @ Sanford Marina
Bid No.: 12/13-18
Owner: City of Sanford
Contractor: S.E. Cline Construction, Inc.
Agreement Date: July 22, 2013
This Certificate of Final Completion applies to all work under the Contract Documents or the
following specified parts thereof if construction is phased by contract:
ISSUED TO:
Contractor:
S.E. Cline Construction, Inc.
The work to which this Certificate applies has been inspected by authorized representatives of
Contractor, Engineer, and Owner and that Work is hereby declared to be finally complete in
accordance with the Contract Documents on:
November 7, 2013
Date of Final Completion
This Certificate constitutes an acceptance of Work except any and all latent defects, warranty
work, maintenance, and other post Final Completion obligations of the Contractor under the
Contract Documents.
Executed by Engineer on I ( / 0 /Z0f 3
Date
Engineer: CPHH Inc.
(Signature) s
David A. Terwilleger, Project Manager
(Printed Name and Title
Public Dock Facility CERTIFICATE OF FINAL COMPLETION
@ Sanford Marina 00627-1
SPECLIB010704
1.
Contractor accepts this Certificate of Final Completion on // 2✓ 2,1.3
D e
Contractor: S„E. ft,,,- s"ewdcv) ✓ G.
By: Zi ,., . 1(.r
(Signature)
(Printed Name and Title)
Accepted by Owner on 1 i for/
Date
Owner: CITY OF SANFORD
By:
(Signatu )
Tom George / Deputy City Manager
(Printed Name and Title)
END OF SECTION
Public Dock Facility CERTIFICATE OF FINAL COMPLETION
@ Sanford Marina 00627-2
SPECLIB010704