Loading...
1570* Vogel Bros PO 33336HIM Monday, December 01, 2014 -1 77-9 To: City Clerk RE: Vogel Bros Build CO PO 33336 Change Order 5 increase PO for $6,778.58 IFB 12/13-05 Sanford Water Treatment Plant No. 2 DBP Compliance Improvement The item(s) noted below is/are attached and forwarded to your office for the following action(s): ❑ Development Order ❑ Mayor's signature ❑ Final Plat (original mylars) ❑ Recording ❑ Letter of Credit ❑ Rendering ❑ Maintenance Bond ® Safe keeping (Vault) ❑ Ordinance ❑ Deputy City Manager ❑ Performance Bond ❑ Payment Bond ❑ Resolution ❑ City Manager Signature ❑ ❑ City Clerk Attest/Signature Once completed, please: ❑ Return originals to Purchasing ❑ Return copies El Special Instructions: Ma4-i64-t, Ord. -i7 From Date T:\Dept_forms\City Clerk Transmittal Memo - 2009.doc iw;Csf Iraq, DATE: 04/03/13 PURCHASING OFFICE: 407.688.5030 ACCOUNTS PAYABLE: 407.688.5020 FACSIMILE: 407.688.5021 VENDOR NO.: 11887 WPM VOGEL BROS BUILDING CO 2720 DRANE FIELD RD LAKELAND, FL 33811 PURCHASE ORDER CITY OF SANFORD P.O. BOX 1788 (300 NORTH PARK AVENUE) SANFORD, FLORIDA 32772 FLORIDA TAX EXEMPT NO.: 858012621681 C-8 PO NUMBER 033336 CHANGE #: 15 DATE CHG: 04/18/13 SUBMIT INVOICES TO: ACCOUNTS PAYABLE FINANCE DEPT. P.O. BOX 1788 SANFORD, FL 32772 SHIP TO: CITY OF SANFORD 300 N. PARK AVENUE SANFORD, FL 32771 DELIVER BY TERMS F.O.B. DESTINATION BID OR QUOTATION NO. REQUISITION NO. UNLESS OTHERWISE INDICATED 09/30/13 NET 63695 ACCOUNT NO.: 452-4530-536.63-03 PROJECT NO.: DW110 3 NO DEVIATION FROM THIS PURCHASE ORDER WILL BE ALLOWED UNLESS AUTHORIZED, BY THE PURCHASING MANAGER - CITY OF SANFORD ITEM NO. DESCRIPTION QUANTITY OF UNITE ISSUE UNIT COST EXTENDED COST *ic9t9cir�e�c�ryF�e�cF**icicki::t�c*7F�r**ic9: icicic*9c�c9c * CHANGE ORDER 1 WTP DISINFECTION BY PRODUCTS WTP 6900000.00 NA 1.00 6900000.00 2 CONTRACTOR IFB 12/13-05 COMPLIANCE IMPROVEMENTS CPH JOB NO. 506118.1 Change Order to save sales taxes $ on ODP Purchases " TAX SAVING OF A TOTAL OF $162,328 DEDUCTIVE CHANGE ORDER TOTAL $2,705,465 2 ODP PURCHASE FOR GREAT SOUTHERN 150000.00- NA 1.00 150000.00• - PUMP #REQ5.1236 Tax Savings of $9,000 3 ODP PINNACLE OZONE SOLUTIONS LLC 641000.00- NA 1.00 641000.00- REQ1-1236 Tax Savings of $38,460 4 ODP GUARDIAN EQUIPMENT INC REQ 96500.00- NA 1.00 96500.00- 2.1236 Tax Savings $5,790 5 ODP XYLEM INC FLYGY PRODUCTS REQ 75368.00- NA 1.00 75368.00- 3.1236 Tax Savings of $4,522 6 ODP CONSOLIDATED ELECTRICAL DIST 149747.17- NA 1.00 149747.17 - INC REQ 6.1236 Tax Savings of $8,985 APPROVED B — APPROVED BY: r — PU SING A N CITY ANAGER ALL PACKA AND INVOICES ASSOCIATED WITH THIS P.O. MUST BEAR THIS PURCHASE ORDER NUMBER. THE VENDOR IS RESPONSIL READ AND COMPLY WITH ALL OF THE STANDARD TERMS AND CONDITIONS PROVIDED ON THE REVERSE SIDE OF THIS PURCHAL AND AT HTTP://WWW.SANFORDFL.GOV/DEPARTMENTS/PURCHASE/TERMS.HTML COPIES TO: VENDOR ORIGINATING DEPARTMENT PURCHASING DATE: 04/03/13 PURCHASING OFFICE: 407.688.5030 ACCOUNTS PAYABLE: 407.688.5020 FACSIMILE: 407.688.5021 VENDOR NO.: 11887 PURCHASE ORDER CITY OF SANFORD P.O. BOX 1788 (300 NORTH PARK AVENUE) SANFORD, FLORIDA 32772 FLORIDA TAX EXEMPT NO.: 858012621681 C-8 PO NUMBER 033336 CHANGE #: 15 DATE CHG: 04/18/13 SUBMIT INVOICES TO: ACCOUNTS PAYABLE FINANCE DEPT. P.O. BOX 1788 SANFORD, FL 32772 TO. SHIP TO. VOGEL BROS BUILDING CO CITY OF SANFORD 2720 DRAKE FIELD RD 300 N. PARK AVENUE LAKELAND, FL 33811 _SANFORD, FL 32771 DELIVER BY TERMS F.O.B. DESTINATION BID OR QUOTATION NO. REQUISITION NO. UNLESS OTHERWISE INDICATED 09/30/13 NET 63695 ACCOUNT NO.: 452-4530-536.63-03 PROJECT NO.: DW 110 3 NO DEVIATION FROM THIS PURCHASE ORDER WILL BE ALLOWED UNLESS AUTHORIZED BY THE PURCHASING MANAGER - CITY OF SANFORD ITEM NO. DESCRIPTION QUANTITY UNIT OF ISSUE UNIT COST EXTENDED COST iir*�r�ricic�*��*�*4: 9c�ciric9cirir*kSY*Yic�c�ek�cicY * CHANGE ORDER 7 ODP CALGON CARBON CORP REQ 1473000.00- NA 1.00 1473000.00- 4.1236 Tax Savings of $88,380 8 ODP PURCHASE RING POWER CORP REQ 119850.00- NA - 1.00 119850.00- 7.1236 Tax Savings of $7,191 9 ACCUMULATED TAX SAVINGS 162327.91- NA 1.00 162327.91 - APPLICABLE TO LINE ITEMS 2-thru 8 total savings of $162,327.91 10 ODP GREAT SOUTHERN PUMP REQ 50085.00- NA 1.00 50085.00- -8-1236 TAX SAVINGS Tax Savings of $2,835 11 ORDER PUMPS (CHANGE ORDER) .00 .00 .00 12 REMOVAL OF UNSUITABLE MATERIAL .00 .00 .00 13 WTP DISINFECTION BY PRODUCTS WTP 621682.73 NA 1.00 621682.73 2 CONTRACTOR IFB 12/13-05 COMPLIANCE IMPROVEMENTS CPH JOB NO.SO6118.1 ASR MODIFICATIONS $249,826.41 (0) DAYS APPROVED BY: APPROVED BY: PURCHASING AGENT CITY MANAGER ALL PACKAGES AND INVOICES ASSOCIATED WITH THIS P.O. MUST BEAR THIS PURCHASE ORDER NUMBER. THE VENDOR IS RESPONSIBLE TO CAREFULLY READ AND COMPLY WITH ALL OF THE STANDARD TERMS AND CONDITIONS PROVIDED ON THE REVERSE SIDE OF THIS PURCHASE ORDER AND AT HTTP://WWW.SANFORDFL.GOV/DEPARTMENTS/PURCHASErrERMS.HTML COPIES TO: VENDOR ORIGINATING DEPARTMENT PURCHASING DATE: 04/03/13 PURCHASING OFFICE: 407.688.5030 ACCOUNTS PAYABLE: 407.688.5020 FACSIMILE: 407.688.5021 PURCHASE ORDER CITY OF SANFORD P.O. BOX 1788 (300 NORTH PARK AVENUE) SANFORD, FLORIDA 32772 FLORIDA TAX EXEMPT NO.: 858012621681 C-8 VENDOR NO.: 11887 TO: VOGEL BROS BUILDING CO 2720 DRAKE FIELD RD LAKELAND, FL 33811 PO NUMBER 033336 CHANGE #: 15 DATE CHG: 04/18/13 SUBMIT INVOICES TO: ACCOUNTS PAYABLE FINANCE DEPT. P.O. BOX 1788 SANFORD, FL 32772 SHIP TO: CITY OF SANFORD 300 N. PARK AVENUE SANFORD, FL 32771 DELIVER BY TERMS F.O.B. DESTINATION BID OR QUOTATION NO. REQUISITION NO. UNLESS OTHERWISE INDICATED 09/30/13 NET 63695 ACCOUNT NO.: 452-4530-536.63-03 PROJECT NO.: DW1103 NO DEVIATION FROM THIS PURCHASE ORDER WILL BE ALLOWED UNLESS AUTHORIZED BY THE PURCHASING MANAGER - CITY OF SANFORD ITEM NO. DESCRIPTION QUANTITY UNIT OF ISSUE UNIT COST EXTENDED COST aY*SY�cY9s�rk�ricY*ir�c*ic9rickt****9c*FY 9cic*ic9c�e . * CHANGE ORDER LIQUID OXYGEN SYSTEMS $371,856.32 (42)DAYS IN CHANGE OF PO SUBSTANCIAL COMPLETION DATE WILL BE JUNE 4, 2014 CHANGE ORDER NO.2 Chane Order NO. 2 is change to add 9621,682.93 to add the ASR System Modification and "Liquid Oxygen System. Removed item no. 11 & 12 not 14 INCREASE PO 33336 CHANGE ORDER 274937.90 NA 1.00 274937.90 NO. 3 SWTP NO. 2 IFB 12/13-05; COMPLIANCE IMPROVEMENTS HIGH SERVICE PUMP SYSTEMS MODIFICATIONS; THE DESIGN CAPACITY OF THE NEW OZONE GAC TREATMENT PROCESS IS 4.5MGD. IT WILL BE NECESSARY TO UPGRADE THE EXISTING HIGH SERVICE PUMPS TO MATCH THE 4.5 MGD PLANT CAPACITY TO COMPENSATE FOR PLANT #1 SEE ATTACHED CHANGE ORDER NO 3 Add an additional Fee to line no. APPROVED BY: APPROVED BY: PURCHASING AGENT CITY MANAGER ALL PACKAGES AND INVOICES ASSOCIATED WITH THIS P.O. MUST BEAR THIS PURCHASE ORDER NUMBER. THE VENDOR IS RESPONSIBLE TO CAREFULLY READ AND COMPLY WITH ALL OF THE STANDARD TERMS AND CONDITIONS PROVIDED ON THE REVERSE SIDE OF THIS PURCHASE ORDER AND AT HTTP:1/WWW.SANFORDFL.GOV/DEPARTMENTS/PURCHASEfTERMS.HTML COPIES TO: VENDOR ORIGINATING DEPARTMENT PURCHASING DATE: 04/03/13 PURCHASING OFFICE: 407.688.5030 ACCOUNTS PAYABLE: 407.688.5020 FACSIMILE: 407.688.5021 VENDOR NO.: 11887 TO: VOGEL BROS BUILDING CO 2720 DRANE FIELD RD LAKELAND, FL 33811 PURCHASE ORDER CITY OF SANFORD P.O. BOX 1788 (300 NORTH PARK AVENUE) SANFORD, FLORIDA 32772 FLORIDA TAX EXEMPT NO.: 858012621681 C-8 PO NUMBER 033336 CHANGE #: 15 DATE CHG: 04/18/13 SUBMIT INVOICES TO: ACCOUNTS PAYABLE FINANCE DEPT. P.O. BOX 1788 SANFORD, FL 32772 SHIP TO: CITY OF SANFORD -300 N. PARK AVENUE SANFORD, FL 32771 DELIVER BY TERMS F.O.B. DESTINATION BID OR QUOTATION NO. REQUISITION NO. UNLESS OTHERWISE INDICATED 09/30/13 NET 63695 ACCOUNT NO.: PROJECT NO.: 452-4530-536.63-03 DW1103 NO DEVIATION FROM THIS PURCHASE ORDER WILL BE ALLOWED UNLESS AUTHORIZED BY THE PURCHASING MANAGER -CITY OF SANFORD ITEM NO. DESCRIPTION QUANTITY UNIT OFISSUE UNIT COST EXTENDED COST * * CHANGE ORDER 10 of $5,093.00 - to increase PO 33529 a total of $55,093.00 completed by CPH still ending... adjusted to p$50,008.50 15 CHANGE ORDER NO.4 RAW WATER 39000.00 NA 1.00 39000.00 CONNECTION TIME EXT $35,000 AND THE SITE SAFETY UPGRADES & TIME'EXT FOR $34,236.58; ITEM NO.2 & 3 ARE A CREDIT TO THE PO MISC CASH ALLOWANCE OF $-30,000 AND ODP OF HIGH SERVICE PUMPS TAX SAVINGS $-50,085.00 (CREDITS) ADDING THE HAULING & DISPOSAL OF UNSUITABLE MATERIAL FORM THE WATER PLANT SITE AT $39,000 CHANGE ORDER NO. 1 16 MISC ITEMS FOR FACILITY CASH 30000.00- NA 1.00 3000.0.00 - ALLOWANCE RETURNED 17 RAW WATER CONNECTION TIME 69236.58 NA 1.00 69236.58 EXTENSION-& SITE SAFETY IMPROVEMENTS & EXTENSION... APPROVED BY: PURCHASING AGENT APPROVED BY: CITY MANAGER ALL PACKAGES AND INVOICES ASSOCIATED WITH THIS P.O. MUST BEAR THIS PURCHASE ORDER NUMBER. THE VENDOR IS RESPONSIBLE TO CAREFULLY READ AND COMPLY WITH ALL OF THE STANDARD TERMS AND CONDITIONS PROVIDED ON THE REVERSE SIDE OF THIS PURCHASE ORDER AND AT HTTP://WWW.SANFORDFL.GOV/DEPARTMENTS/PURCHASE/TERMS.HTML COPIES TO: VENDOR ORIGINATING DEPARTMENT PURCHASING DATE: 04/03/13 PURCHASING OFFICE: 407.688.5030 ACCOUNTS PAYABLE: 407.688.5020 FACSIMILE: 407.688.5021 VENDOR NO.: 11887 PURCHASE ORDER PO NUMBER 033336 CITY OF SANFORD CHANGE #: 15 P.O. BOX 1788 DATE CHG : 04/18/13 (300 NORTH PARK AVENUE) SUBMIT INVOICES TO: ACCOUNTS PAYABLE SANFORD, FLORIDA 32772 FINANCE DEPT. FLORIDA TAX EXEMPT NO.: 858012621681 C-8 P.O. BOX 1788 SANFORD,FL32772 TO: SHIP TO: VOGEL BROS BUILDING CO CITY OF SANFORD 2720 DRANE FIELD RD 300 N. PARK AVENUE LAKELAND, FL 33811 SANFORD, FL 32771 DELIVER BY TERMS F.O.B. DESTINATION BID OR QUOTATION NO. REQUISITION NO. UNLESS OTHERWISE INDICATED 09/30/13 NET 63695 ACCOUNT NO.:PROJECT NO.: 452-4530-.536.63-03 DW1103 NO DEVIATION FROM THIS PURCHASE ORDER WILL BE ALLOWED UNLESS AUTHORIZED BY THE PURCHASING MANAGER - CITY OF SANFORD ITEM NO. DESCRIPTION QUANTITY UNIT OF ISSUE UNIT COST EXTENDED COST ick**�Y*iek*k4r *�F*ic 9c �t&k �r �Y is*'3c is 4c **�t k*�: 4r 9c * CHANGE ORDER RW -$35,000 , SS - $34,236.58 A TOTAL OF $69,236.58 INCREASE ON PO 18 CPH JOB NO. S06118.2 INCREASE PO 6778.58 NA, 1.00 6778.58 Change Order No. 5 line 1-thru 19 misc items SUB TOTAL 4963757.71 TOT L 4963757.71 APPROVED BY: PURCHASING AGENT APPROVED BY: CITY MANAGER ALL PACKAGES AND INVOICES ASSOCIATED WITH THIS P.O. MUST BEAR THIS PURCHASE ORDER NUMBER. THE VENDOR IS RESPONSIBLE TO CAREFULLY READ AND COMPLY WITH ALL OF THE STANDARD TERMS AND CONDITIONS PROVIDED ON THE REVERSE SIDE OF THIS PURCHASE ORDER AND AT HTTP://WWW.SANFORDFL.GOV/DEPARTMENTS/PURCHASErTERMS.HTML COPIES TO: VENDOR ORIGINATING DEPARTMENT PURCHASING City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-1 CPH Job No. S06118.2 SECTION 00950 CHANGE ORDER FORM Change Order No. 5 $ 6,900,000.00 Project Name: Sanford WTP No. 2 DBP Compliance Improvements $ 4,956,979.13 Bid No.: IFB 12/13-05 $ 6,778.58 Owner: City of Sanford $ 4,963,757.71 Contractor: Vogel Bros. Building Co. 365 Days Agreement Date: February 28, 2013 This Change Order is necessary to cover changes in the work to be performed under this Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS apply to and govern all work under this Change Order. THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS: (1) Original Contract Price $ 6,900,000.00 (2) Current Contract Price $ 4,956,979.13 (3) Total Proposed Change in Contract Price $ 6,778.58 (4) New Contract Price (Item 2 + Item 3) $ 4,963,757.71 (5) Original Contract Time 365 Days (6) Current Contract Time (Adjusted by Previous Change Orders) 496 Days (7) Total Proposed Change in Contract Time 0 Days (8) New Contract Time (Item 6 + Item 7) 496 Days (9) New Contract Substantial Completion Date August 19, 2014 CHANGES ORDERED November 2012 Change Order Form City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-2 CPH Job No. S06118.2 ITEM 1 Description of Change: ASR Feed Pipeline Design Modifications Reason for Change: Elimination of motorized valves, flow meters, pressure reducing valves, and associated electrical and instrumentation. Change in Contract Price: $80,544.00 Change in Contract Time: 0 Days ITEM 2 Description of Change: Actual Cost — Unsuitable Materials Reason for Change: To reconcile the difference between the actual costs of the unsuitable materials removed and the previously estimated amount approved in Change Order No. 1. Change in Contract Price: $8,092.00 Change in Contract Time: 0 Days ITEM 3 Description of Change: High Service Pump Building Lintel Replacement Reason for Change: To remove and replace failing lintel at High Service Pump Building Change in Contract Price: $3,631.05 Change in Contract Time: 0 Days ITEM 4 Description of Change: GAC Electrical Revisions Reason for Change: Upon Calgon GAC Shop Drawing review design revisions including upsizing of control wires and increasing breaker sizes. November 2012 Change Order Form City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-3 CPH Job No. S06118.2 This cost also includes eliminating the generator remote annunciator panel and adding fiber optic cable from the generator to the PLC panel. Change in Contract Price: $11,886.00 Change in Contract Time: 0 Days ITEM 5 Description of Change: Ground Storage Tank MJ Plug Reason for Change: To furnish and install a 20" DI MJ Plug to facilitate renovations to the 0.5 MG Ground Storage Tank. Change in Contract Price: $894.50 Change in Contract Time: 0 Days ITEM 6 Description of Change: Ground Storage Tank Baffle Wall Modifications Reason for Change: Deduct for the elimination of demolition of portions of existing baffle wall in Ground Storage Tank. Change in Contract Price: $609.00 Change in Contract Time: 0 Days ITEM 7 Description of Change: Duplex Air Compressors Reason for Change: Cost to utilize a duplex air compressor system in lieu of a singular system. The duplex system will provide the City more flexibility for Operations and Maintenance and give the Ozone and GAC systems dedicated units. Change in Contract Price: $4,397.96 November 2012 Change Order Form City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-4 CPH Job No. S06118.2 Change in Contract Time: 0 Days ITEM 8 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 9 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 10 Description of Change Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 11 Generator Enclosure Stairs To furnish and install one set aluminum stairs and landings to access the Generator Enclosure Interior $8,873.00 0 Days Ground Storage Aerator Cap To furnish and install a 20" Carbon Steel cap on the existing Aerator piping connection to the ground storage tank. $2,162.80 0 Days Room 106 Additional Masonry To increase the masonry wall height from 9'0" AFF to 10'0" in Room 106. $978.00 0 Days November 2012 Change Order Form City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-5 CPH Job No. S06118.2 Description of Change: 10" Raw Water Interconnection Change Reason for Change: Additional costs associated with 10" fittings at the Raw Water Interconnection originally specified as 12" in diameter. Change in Contract Price: $6,122.33 Change in Contract Time: 0 Days ITEM 12 Description of Change: Added Trees and Irrigation System Reason for Change: To furnish and install (38) Eastern Red Cedar Trees and associated irrigation along north and east fence lines. Change in Contract Price: $13,363.00 Change in Contract Time: 0 Days ITEM 13 Description of Change: High Service Pump Station and Raw Water Connection Design Changes Reason for Change: The costs associated with labor, equipment, and materials associated with High Service Pump Station and Raw Water Connection design changes. Change in Contract Price: $18,784.00 Change in Contract Time: 0 Days ITEM 14 Description of Change: GAC Pressure Switches Reason for Change: Cost associated with the electrical work associated with the installation of six (6) differential pressure switches to the GAC system. November 2012 Change Order Form City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-6 CPH Job No. S06118.2 Change in Contract Price: $6,161.68 Change in Contract Time: 0 Days ITEM 15 Description of Change Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 16 Description of Change Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 17 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: Recoating of GAC Piping To recoat the factory painted GAC system piping to colors selected by owner to facilitate ease of operation. $7,977.92 0 Days Data Revisions Addition of CAT6 cables to accommodate the HMI Network, Security System, and City Network. To handle the cable count increase an additional ethernet switch was required. $7,301.49 0 Days AHU Fused Disconnect Added to provide means of disconnection for AHU-1. $367.25 0 Days November 2012 Change Order Form City of Sanford—, WTP No. 2 Disinfection By -Products Compliance Improvements 00950-7 CPH Job No. S06118.2 ITEM 18 Description of Change: Added Operator Work Station Desks Reason for Change: Added to provide the operators sufficient area to work. Original layout provided cabinets without room for work stations. Change in Contract Price: $2,500.56 Change in Contract Time: 0 Days Description of Change: Destruct Blower Ball Valve Reason for Change: Added to provide protection to the Destruct System from water at the high water level at the Ozone Contact Tank. Change in Contract Price: $632.04 Change in Contract Time: 0 Days November 2012 , Change Order Form City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-8 CPH Job No. S06118.2 WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly and indirectly from the change. Acceptance of this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change Order. November 2012 Change Order Form CHANGE ORDER SUMMARY No. Description Change in Contract Price Change in Contract Time 1 ASR Feed Pipeline Design Modifications $80,544.00 0 days 2 Actual Cost — Unsuitable Materials $8,092.00 0 days 3 High Service Pump Building Lintel Replacement $3,631.05 0 days 4 GAC Electrical Revisions $11,886.00 0 days 5 Ground Storage Tank MJ Plug $894.50 0 days 6 Ground Storage Tank Baffle Wall Modifications $609.00 0 days 7 Duplex Air Compressors $4,397.96 0 days 8 Generator Enclosure Stairs $8,873.00 0 days 9 Ground Storage Aerator Cap $2,162.80 0 days 10 Room 106 Additional Masonry $978.00 0 days 11 10" Raw Water Interconnection Chane $6,122.33 0 days 12 Added Trees and Irrigation System $13,363.00 0 days 13 High Service Pump Station and Raw Water Connection Design Changes $18,784.00 0 days 14 GAC Pressure Switches $6,161.68 0 days 15 Recoating of GAC Piping $7,977.92 0 days 16 Data Revisions $7,301.49 0 days 17 AHU Fused Disconnect $367.25 0 days 18 Added Operator Work Station Desks $2,500.56 0 days 19 Destruct Blower Ball Valve $632.04 0 days TOTAL $ 6,778.58 0 Days WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly and indirectly from the change. Acceptance of this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change Order. November 2012 Change Order Form City of Sanford — WTP No. 2 Disinfection By -Products Compliance Improvements 00950-9 CPH Job No. S06998.2 APPROVAL AND CHANGE ORDER AUTHORIZATION ACKNOWLEDGMENTS The aforementioned change, and work affected thereby, is subject to all provisions of the original Agreement and specifically changed by this Change Order; and It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original Agreement other than matters expressly provided herein. WITNESS to CONTRACTOR: Vogel Bros. Building Co.. Contractor KA -1-q \ w D' William Bocchino VP of Operations Prin d Name and Title Off* er 4� � P7a Date Ey (Si -gin ature) November 3, 2014 Date (Corporate Seal) ATTEST: p Owner (Sign ture) Printed Name and Title Date By (Sign. ure) i J%zi 7 (Seal) Date November 2012 Change Order Form City of Sanford— WTP No. 2 Disinfection BV -Products Compliance Improvements 00950-1 CPH Job No. S06118.2 SECTION 00950 CHANGE ORDER FORM Change Order No. 1 $ 6,900,000.00 (2) Project Name: Sanford WTP No. 2 DBP Compliance Improvements (3) Total Proposed Change in Contract Price Bid No., IFB 12/13-05 New Contract Price (item 2 + Item 3) $ 4,071,206.92 Owner: City of Sanford 365 Days (6) Contractor: Vogel Bros. Building Co. (7) Total Proposed Change in Contract Time Agreement Date: February 28, 2013 This Change Order is necessary to cover changes in the work to be performed under this Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS apply to and govern all work under this Change Order. - THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS: (1) Original Contract Price $ 6,900,000.00 (2) Current Contract Price $ 6,900,000.00 (3) Total Proposed Change in Contract Price ($.2,828,793.08) (4) New Contract Price (item 2 + Item 3) $ 4,071,206.92 (5) Original Contract Time 365 Days (6) Current Contract Time (Adjusted by Previous Change Orders) 365 Days (7) Total Proposed Change in Contract Time 14 Days (8) New Contract Time (Item 6 + Item 7) 379 Days (9) New Contract Substantial Completion Date April 23, 2014 November 2012 Change Order Form City of Sanford— WTP No. 2 Dlslnfection By -Products Compliance Improvements 00950-2 CPH Job No. S0611&2 Description of Change: Owner direct purchase and tax savings Reason for Change: Tax savings on owner direct purchase items Change in Contract Price: $2,867,793.08 Change in Contract Time: 0 ITEM 2 Description of Change: Hauling and disposal of unsuitable material from the plant site Reason for Change: To facilitate the construction of ozone contact tank and the storm .water retention pond Change in Contract Price: $ 39,000.00 Change in Contract Time: 14 days CHANGE ORDER SUMMARY No. Description Change in Contract Price Change in Contract Time 1 City Direct purchase and tax savings $2,867,793.68 14 days 2 Hauling and disposal of unsuitable material from the water plant site $39,000.00 TOTAL $ 2,828,793.08 14 Davs WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly and indirectly from the change. Acceptance of this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change Order. November 2012 Change Order Form I City of Sanford - WTP No. 2 Disinfection By!Products Compliance Improvements 00950.3 CPH Job No. S06118.2 APPROVAL AND CHANGE ORDER AUTHORIZATION ACKNOWLEDGMENTS The aforementioned change, and work affected thereby, is subject to all provisions of the original Agreement and specifically changed by this Change Order; and - It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original Agreement other than matters expressly provided herein. WITNESS to CONTRACTOR: June 12, 2013 Date Vogel Bros. Building Co. Contractor Printed N ,Mnd Tit Officer Operations ��'1IMM 12, /2013 (Corporate Seal) ATTEST: CITY cF .�/j.vF�ea Owner (oY� GI=U:G�' AL•iu7Y Cir/ /'�/�."��'`K' (Signature) Printed Name and Title Date By (Sig Lure) // 9 I� (Seal) Date END OF SECTION November 2012 Change Order Form City of Sanford — WTP No. 2 Disinfection By -Products Compliance Improvements ---- 00950-1 CPH Job No. S06118.2 SECTION 00950 CHANGE ORDER FORM Change Order No. 2 $ 6,900,000-00 (2) Project Name: Sanford WTP No. 2 DBP Compliance Improvements (3) Total Proposed Change in Contract Price Bid No.: IFB 12/13-05 New Contract Price (item 2 + Item 3) $ 4,692,889.65 Owner: City of Sanford 365 Days (6) Contractor: Vo el Bros. Building Co. (7) Total Proposed Change in Contract Time Agreement Date: February 28, 2013 This Change Order is necessary to cover changes in the work to be performed under this Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS apply to and govern all work under this Change Order. THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS: (1) Original Contract Price $ 6,900,000-00 (2) Current Contract Price $ 4,071,206.92 (3) Total Proposed Change in Contract Price $ 621,682.73 (4) New Contract Price (item 2 + Item 3) $ 4,692,889.65 (5) Original Contract Time 365 Days (6) Current Contract Time (Adjusted by Previous Change Orders) 379 Days (7) Total Proposed Change in Contract Time 42 Days (8) New Contract Time (item 6 + Item 7) 42.1., Days (9) New Contract Substantial Completion Date June 4, 2014 CHANGES ORDERED November 2012 Change Order Form City of Sanford — WTP No 2 Disinfection By -Products Compliance Improvements 00950-2 CPN Job No. S0611&2 Description of Change: ASR System Modifications Reason for Change: Modifications to the current system providing water to the ASR are necessary, as part of the V TP #2 upgrades include utilizing the existing ASR feed piping to deliver raw water to the treatment process. The proposed 12" potable water line feeding the ASR will come from an existing 18" water distribution line located at Airport Blvd. A valve will be closed along Airport Blvd. to make sure the potable water leaving the Aux Plant is delivered to the distribution system (hydraulically directed away from Airport Blvd). This new source water will be coming from WTP #1 to assist with the ASR recharge and augmentation needed to produce the maximum treated water from WTP #2. A copy of the contractor's proposal is included for your use. The hydraulic issues encountered by using the existing potable line were an oversight from the City and not evaluated during the design. At this time it is important we proceed with this changes to use this WTP at designed capacity. Change in Contract Price: $249,826.41 Change in Contract Time: 0 Days ITEM 2 Description of Change: Furnish and install a "turn -key" Liquid Oxygen System including all equipment, installation, start-up, and testing Reason for Change: The Liquid Oxygen System is an integral part of the ozonation treatment process. The original bid included only the equipment pad as the City's plan was to piggy -back into an existing contract with a "built/supplier" liquid oxygen vendor. After several months of researching for a contract to piggy -back, the City learned that this type of contract was not available. Due to the type of contract needed being unavailable, Vogel was instructed to incorporate the liquid oxygen system into their scope of work. Change in Contract Price: $371,856.32 Change in Contract Time: 42 Days (Based on approval no later than 12/15/13) November 2012 Change Or rm City of Sanford WTP No 2 Disinfection By -Products Compliance Improvements 00930-3 CPH Job No. S06118.2 CHANGE ORDER SUMMARY No. Description Change in Contract Price Change in Contract Time 1 ASR System Modifications $249,826.41 0 days 2 Liquid Oxygen System $371,856.32 42 days TOTAL $ 621,682.73 42 Days WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly and indirectly from the change. Acceptance of this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change Order. November 2012 Change Order Form City of Sanford WTP No 2 Disinfection By -Products Compliance Improvements 00950-4 CPH Job No. S061 M2 APPROVAL AND CHANGE ORDER AUTHORIZATION ACKNOWLEDGMENTS The aforementioned change, and work affected thereby, is subject to all provisions of the original Agreement and specifically changed by this Change Order; and It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original Agreement other than matters expressly provided herein. WITNESS to CONTRACTOR: 3 Date ATTEST: I ?--Cl— Cs Date (Seal) Vogel Bros. Building Co. Contractor of Officer Seal) Owner i %o Y Printed Name and Title By (Signature) I 2 --- Ct — 1 Z Date November 2012 Change Order Form City of Sanford — WTP No. 2 Disinfection By -Products Compliance Improvements 00950-1 CPN Job No. S06118.2 SECTION 00950 CHANGE ORDER FORM Change Order No. 3 $ 6,900,000.00 (2) Project Name: Sanford WTP No. 2 DBP Compliance Improvements (3) Total Proposed Change in Contract Price Bid No.: IFB 12/13-05 New Contract Price (Item 2 + Item 3) $ 4,967,827.55 Owner: City of Sanford 365 Days (6) Contractor: Vogel Bros. Building Co. (7) I Agreern 28, 2013 This Change Order is necessary to cover changes in the work to be performed under this Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS apply to and govern all work under this Change Order. THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS' (1) Original Contract Price $ 6,900,000.00 (2) Current Contract Price $ 4,692,889.65 (3) Total Proposed Change in Contract Price $ 274,937.90 (4) New Contract Price (Item 2 + Item 3) $ 4,967,827.55 (5) Original Contract Time 365 Days (6) Current Contract Time (Adjusted by Previous Change Orders) 421 Days (7) Total Proposed Change in Contract Time 0 Days (8) New Contract Time (Item 6 + Item 7) 421 Days (9) New Contract Substantial Completion Date June 4, 2014 CHANGES ORDERED November 2012 Change Order Form City of Sanford - WTP No. 2 Disinfection By -Products Compliance Improvements 00950-2 CPH Job No. S06118.2 ITEM 't Description of Change: High Service Pump System Modifications Reason for Change: The design capacity of the new Ozone/GAC treatment process is 4.5 MGD. It will be necessary to upgrade the existing high service pumps to match the 4.5 MGD plant capacity to compensate for Plant #1 construction delays due to lack of funding. It is proposed to replace the two existing high service pumps with two (2) new 125 HP pumps, each with 3.5 MGD capacity at 140 feet discharge head. One of the existing larger pumps will serve as a spare unit. New variable frequency drives and power feed to the two new pumps will be designed and installed. Pump control will be modified to provide flexibility in high service pumps operation for meeting the finished water demands. Due to the increase in plant capacity, it is necessary to replace the existing 12 inch high service pump discharge with a larger pipe. A new 18 inch pipe will be installed which will extend from the high service pump station and connect to an existing water main outside the plant on US 17-92. Change in Contract Price: $274,937.90 Change in Contract Time: 0 Days November 2012 Change order Form City of Sanford — WTP No. 2 Disinfection By!Products Compliance Improvements 00950-3 CPH Job No. S06118.2 CHANGE ORDER SUMMARY No. Description Changein Contract Price Changein Contract Time I High Service Pump System Modifications $ 274,937.90 0 days TOTAL $ 274,937.90 0 Days WAIVER This Change Order constitutes full and mutual accord and oebafuoUon for the adjustment of the Contract Price and Contract Time as m naaub of increases or decreases in oocd and time of performance caused directly and indirectly from the change. A000utenue of this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order naprmmmnia an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights tofile m Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CDNTRACTOF[m complete acceptance and satisfaction that it is anUUad to no more unab; or time (dinac%, indinact, imnpact, etc.) pursuant to this Change Order. November 2012 Change Order Form City of Sanford — WTP No. 2 Disinfection By -Products Compliance Improvements 00950-4 CPH Job No, S06198.2 ,�...* a z �• �� ACKNOWLEDGMENTS The aforementioned change, and work affected thereby, is subject to all provisions of the original Agreement and specifically changed by this Change Order; and It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original Agreement other than matters expressly provided herein. WITNESS to CONTRACTOR: Date ATTEST: (Signatu A) Date (Seal) VO e (- 13Pos, 1 >rt,,-wkh, Cc. Contractor Owner Owner Name and Title t.....,.i l o - crtr~aY By (Signaturd) (��1 Date November 2012 Change Order Form City of Sanford — WTP No. 2 Disinfection Bv-Products Compliance Improvements 00950-1 CPH Job No. S06118.2 SECTION 00960 CHANGE ORDER FORM Change Order No. 4 $ 6,900,000.00 V Project Name; Sanford WTP No. 2 DBP Compliance Improvements (3) Total Proposed Change in Contract Price Bid No.: IFB 12/13-05 New Contract Price (Item 2 + Item 3) $ 4,956,979.13 Owner: City of Sanford 365. Days (6) Contractor: Vo el Bros. Building Co. (7) Total Proposed Change in Contract Time AgreementDate: _February 28, 2013 This Change Order is necessary to cover changes in the work to be performed under -this Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS apply to and govern all work under this Change Order. THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS: (1) Original Contract Price $ 6,900,000.00 (2) Current Contract Price $ 4,967,827.55 (3) Total Proposed Change in Contract Price ($ 10,848.42) (4) New Contract Price (Item 2 + Item 3) $ 4,956,979.13 (5) Original Contract Time 365. Days (6) Current Contract Time (Adjusted by Previous Change Orders) 421 Days (7) Total Proposed Change in Contract Time 75 Days (8) New Contract Time (Item 6 + Item 7) 496 Days (9) New Contract Substantial Completion Date August 19, 2014, CHANGES ORDERED November 2012 Change Order Form (Zkv of Sanford — WTP No. 2 Disinfection By-Praducts Compliance Improvements 00950-2 CPH Job No. S06118.2 ITEM I Description of Owner Direct Purchase o7High Service Pumps Reason for Change: Tax savings on owner direct purchase items Change in Contract Price: -$50,085.00 (credit) Change in Contract Time: 0 Days ITEM 2 Description of Cash Allowance Reason for Change: Toobtain the funds for City use. Change |nContract Price: -$30,000.00 (credit) Change inContract Time: UOoya ITEM 3 Description of Raw Water Connection Time Extension Reason for Time extension of 30 calendar days to the schedule for a new substantial completion date ofJuly 14'3D14omwell aothe costs of extending the schedule by 20 days due to the changes associated with the Raw VVebor piping connections as well as extending the. Change inContract Price: $35.000.00 Change inContract Time: 30 Days November 2012 Change ' City of Sanford — WTP No. 2 Disinfecdon By~ucts Compliance Improvements 00950-3 CPH Job No. S061 M2 Description of Site Safety Upgrades & Time Extension Reason for Change: Furnish and Install (21) additional boUonjo and add 4 foot wide gate at Liquid Oxygen Enclosure to satisfy Liquid Oxygen Supplier Safety Requirements. Time extension of 45 calendar days to the schedule for a new nubotord|a| completion date of Aug as well as the costs of extending the schedule by 30 days due to the changes associated with the Raw \8/abar piping connections ouwell oaextending the. Change inContract Price: $34.236.58 Change inContract Time: 45 Days November 2012 Change Order Form City of Sanford — WTP No. 2 Disinfecdon By -Products Compliance Improvements 00950-4 CPH Job No. S06118.2 WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly d indirectly from the change. this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change November2012 Change Order Form CHANGE ORDER SUMMARY No. Description I Changein Contract Price Changein Contract Time 1 Owner Direct Purchase of High Service Pumps ($50,085.00) 0 days 2 Miscellaneous Cash Allowance ($30,000.00) 0 days 3 Raw Water Connection Time Extension $35,000.00 30 days 4 Site Safety Improvements & Extension $34,236.58 45 days I TOTAL ($10,848.42) 75 Days WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly d indirectly from the change. this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change November2012 Change Order Form City of Sanford — WTP No. 2 Disinfection Bsr-Products Comp/lance Improvements 00950-5 CPU Job No. S06118.2 APPROVAL AND CHANGE ORDER AUTHORIZATION ACKNOWLEDGMENTS The aforementioned change, and work affected thereby, is subject to all provisions of the original Agreement and specifically changed by this Change Order; and It is expressly understood and agreed that the approval of the Change Order shall have no effect on the original Agreement other than matters expressly provided herein. WITNESS to CONTRACTOR: Vogel Bros. Building Co. Contractor _William 1pcchino, Vice President July 9, 2014 Date ATTEST: (Sign ure) 2— Date (Seal) July 9;4--' Date (Corporate Seal) Printed Name and Title By (SigyZZ ture) Date i November 2012 Change Order Form I -0 O O LU LU LU al 4j*j- J/). -V'J. 4JI. qj'). 4j)- jj-p 4j)- 4 , t0 N w T -j w (,o CY) I p -:4 14WWLoWwa%lja 4 -Ph N W Ul NJ a tD a 90 90 V -4 p p p PJ p Ul � W lD W A a a a r) r) r) =r =r 0=r =r =- 0 aj a) W 0:30o ao as Q m rD rD rD rD rD rD > (D 00 "00000OL-. v -3 0 CL C_ " & CL 0- 0- 0- rD (D 0 M M M M M m :m rj Ln w ri FA FA "a > ; 0 0 056 X Ln 3 rD =;. < X. OQ X. =r -V 0 0 EA < 1+ rDrLn+ (D rD c r-) 0 �4 " 5 . 3 0 " CO NJ m = - tj C -V rD a w �.A 3 -a ro 3 0 CL rt rD