793-Maxwell SECTION 00681 CHANGE ORDER FORM Project Title: Country Club Rd./OId Lake Mary Rd. Utility Relocation City IFB No. 98/99-07 Agreement Date: April 26, 1999 Change Order No. 2 (FINAL) Engineer Job No. S0620.04 Contractor: Maxwell Contracting, Inc. Engineer: CPH Engineers, Inc. This Change Order is necessary to cover changes in the work to be performed under this Agreement. The GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS apply to and govern all work under this Change Order. THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS: (1) (2) (3) (4) (5) (6) (7) (8). (9) Original Contract Pdce Current Contract Price (Adjusted By Previous Change Orders) Total Proposed Change in Contract Price New Contract Price (Item 2 plus Item 3) Original Contract Time (Substantial Completion) Current Contract Time (Adjusted By Previous Change Orders) Total Proposed Change in Contract Time New Contract Time (Substantial Completion)(Item 6 plus Item 7) New Construction Substantial Completion Date $ $ $ $ 979,400.00 1,064, 169.65 26,836.82 1,091,006.47 11/30/99 12/30/99 0 DAYS 12/30/99 12/30/99 J:\S0620.04\word\cont\chgord2FINAL.wpd 00681 '1 CHANGES ORDERED ITEM 1 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 2 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 3 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 4 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ADD - 8.104 tons of additional fitting weight for Water Main System (BID ITEM NO. 6) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. Reflects additional fittings required to meet field conditions, plus increased weight of 24" diameter fittings. (Supplier's 24" diameter fittings weigh more than the 24" diameter fitting weights of another supplier used in calculating the pre-construction quantity estimate.) 8.104 Tons @ $3,700.00/Ton = $29,984.80 0 DAYS ADD - 12,5 L,F, of Pipe (DI) F&I (Push on Joint) 6" (BID ITEM NO, 8) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 12.5 L.F. @ $15.00/L.F. = $187.50 0 .DAYS DELETE -75.5 L.F. Pipe (DI) F&I (Push on Joint) 24" (BID ITEM NO. 9) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 75.5 L.F. @ $48.00/L.F. = (-)$3,624.00 0 DAYS DELETE- 10 L.F. Pipe (PVC) F&I (Push on Joint) 12" (BID ITEM NO. 10) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 10 L,F, @ $20,00/L,F, = (-)$200,00 0 DAYS J:\S0620.04\word~ont\chgord2FINALwpd 00681 m2 ITEM 5 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ADD - 2.44 tons of additional fitting weight for Sanitary Force Main System (BID ITEM NO. 20) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. Reflects additional fittings required to meet field conditions. 2.44 tons @ $3300.00FFon = $8,052.00 0 DAYS ITEM 6 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: DELETE - 31.5 L.F. Pipe (PVC) F&I (Push on Joint) 12" (BID ITEM NO, 21) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 31,5 L.F. @ $16.00/L.F. = (-)$504.00 0 DAYS ITEM 7 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ADD - 0.82 tons of additional fitting weight for Reclaimed Water Main System (BID ITEM NO. 24) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 0.82 Tons @ $3950.00/Ton = $3,239.00 0 DAYS ITEM 8 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: DELETE - 107 L.F. Pipe (PVC) (Push on Joint) 14" (BID ITEM NO. 25) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 107 L.F. @ $33.00/L.F. = (-)$3,531.00 0 DAYS J:\S062,0.04%word\cont\chgord2FINAL.wpd 00681-3 ITEM 9 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 10 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 11 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 12 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 13 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: DELETE - Pipe Removal Reclaimed Water Main (BID ITEM NO. 26) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 149 L.F. @ $5.00/L.F. = (-)$745.00 0 DAYS ADD - 2 L.F. Steel Casing (30")(BID ITEM NO. 27) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 2 L.F. @ $80.00/L.F. = $160.00 0 DAYS ADD - 364.5 S.Y. Asphaltic Concrete Type 'S' (1.75") (BID ITEM NO. 29) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 364.5 S.Y. @ $5.25/S.Y. = $1,913.62 0 DAYS DELETE- 102 S.Y. Asphaltic Concrete Type 'S' (1.50") (BID ITEM NO. 30) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 102 S.Y. @ $14.00/S.Y. = (-)$1,428.00 0 DAYS DELETE - 241 S.Y. Asphaltic Concrete Type 'S' (1.25") (BID ITEM NO. 31 ) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 241 S.Y. @ $11.00/S.Y. = (-)$2,651.00 0 DAYS 00681-4 ITEM 14 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 15 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 16 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 17 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 18 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ADD -201.25 S.Y. Limerock Base (10")(BID ITEM NO. 32) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 201.25 S.Y. @ $11.00/S.Y. = $2,213.75 0 DAYS DELETE - 118 S.Y, Limerock Base (8") (BID ITEM NO. 33) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 118 S.Y. @ $9.00/S.Y. = (-)$1,062.00 0 DAYS DELETE - 241 S.Y. Limerock Base (6") (BID ITEM NO. 34) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 241 S.Y. @ $8.00/S.Y. = (-)$1,928.00 0 DAYS DELETE - 423.75 S.Y. Stabilized Subgrade (12") (BID ITEM NO. 35) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 423.75 S.Y. @ $1.00/S,Y. = (-)$423.75 0 DAYS DELETE - 67 S.Y. Remove and Replace Conc. Driveway (BID ITEM NO. 36) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 67 S.Y. @ $20.00/S.Y. = (-)$1,340.00 3 DAYS 00681-5 ITEM 19 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 20 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 21 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 22 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ITEM 23 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: DELETE- 152 S.Y. Remove and Replace Unpaved Driveway (BID ITEM NO. 37) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 152 S.Y. @ $5.00/S.Y. = (-)$760.00 0 DAYS ADD - 28 S.Y. Remove and Replace Concrete Sidewalk (BID ITEM NO. 38) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 28 S.Y. @ $16.00/S.Y. = $448.00 0 DAYS ADD - 5 L.F. Remove and Replace Curb and Gutter (BID ITEM NO. 39) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 5 L.F. @ $12.00/L.F. = $60.00 0 DAYS ADD - 440 S.Y. Sodding (BID ITEM NO. 40) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 440 S.Y. @ $2.00/S.Y. = $880.00 0 DAYS DELETE - 30 L.F. Pipe (D.I.) F&I (Push on Joint) 6" (Change Order No. 1, ITEM NO. 3) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 30 L.F. @ $15,00/L.F. = (-)$450.00 0 DAYS ~':XS0620.04\word\cont\chgord2FINALwpd 00681-6 ITEM 24 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: DELETE - 45 L.F. Pipe (D.I.) F&I (Push on Joint) 24" (Change Order No. 1, ITEM NO. 4) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 45 L.F. @ $48.00/L.F. = (-)$2,160.00 0 DAYS ITEM 25 Description of Change: Reason for Change: Change in Contract Price: Change in Contract Time: ADD - 153 S.Y. 1" Asphalt Type 'S' Overlay (Additive) (Sta 11 +50 to 22+00 and Sta. 25+50 to Sta. 46+00) (Change Order No. 1, ITEM NO. 19) Final adjustment of quantities to reflect actual constructed quantities as adjusted from pre-construction quantity estimate. 153 S.Y. @ $3.30/S.Y. = $504.90 0 DAYS J:\S0620.04\word\cont\¢hgord2FINALwpd 00681-7 ITEM NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 SUMMARY OF CHANGES ORDERED DESCRIPTION Water Main Fittings (D.I.) F&I (8.104 Tons) Pipe (D.I.) F&I (Push on Joint) 6" (12.5 L.F.) DELETE - Pipe (D.I.) F&I (Push on Joint) 24" (75.5 L.F.) DELETE - Pipe (PVC) F&I (Push on Joint) 12" (10 L.F.) Sanitary F.M. Fittings (D.I.) F&I (2.44 Tons) DELETE - Pipe (PVC) F&I (Push on Joint) 12" (31.5 L.F.) Reclaimed W.M. Fittings (D.I.) F&I (0.82 Tons) DELETE - Pipe (PVC) (Push on Joint) 14" (107 L.F.) DELETE- Pipe Removal (149 L.F.) Steel Casing (30") (2 L.F.) Asphaltic Concrete Type 'S' (1.75") (364.5 S.Y.) DELETE - Asphaltic Concrete Type 'S' (1.50") (102 S.Y.) DELETE - Asphaltic Concrete Type 'S' (1.25") (241S.Y.) Limerock Base (10") (201.25 S.Y.) DELETE - Limerock Base (8") (118 S.Y.) DELETE - Limerock Base (6") (241 S.Y.) DELETE - Stabilized Subgrade (12") (423.75 S.Y.) DELETE - Remove and Replace Con. Driveways (67 S.Y.) DELETE - Remove and Replace Unpaved Driveways (152 S.Y.) Remove and Replace Concrete Sidewalk (28 S.Y.) Remove and Replace Curb and Gutter (5 L.F.) Sodding (440 S.Y.) DELETE - Pipe (D.I.) F&I (Push on Joint) 6" (30 L.F.) DELETE - Pipe (D.I.) F&I (Push on Joint) 24" (45 L.F.) 1" Asphalt Type 'S' Overlay (153 S.Y.) TOTAL CHANGE IN CHANGE IN CONTRACT CONTRACT PRICE TIME (DAYS) $29,984.80 0 $187.50 0 ($3,624.00) 0 ($2oo.oo) o $8,052.00 0 ($504.00) 0 $3,239.00 0 ($3,531.00) 0 ($745.00) 0 $160.00 0 $1,913.62 0 ($1,428.00) 0 ($2,651.00) 0 $2,213.75 0 ($1,062.00) 0 ($1,928.00) 0 ($423.75) 0 ($1,340.00) 0 ($760.00) 0 $448.00 0 $60.00 0 $880.00 0 ($450.00) 0 ($2,160.00) 0 $504.90 0 $26,836.82 0 Days J:\S0620.04~.word\cont\chgord2FINAL.wpd 00681-8 WAIVER This Change Order constitutes full and mutual accord and satisfaction for the adjustment of the Contract Price and Contract Time as a result of increases or decreases in cost and time of performance caused directly and indirectly from the change. Acceptance of this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change Order. APPROVAL AND CHANGE ORDER AUTHORIZATION ACKNOWLEDGMENTS The aforementioned change, and work affected thereby, is subject to all provisions of the original Agreement and specifically changed by this Change Order; and it is expressly understood and agreed that the approval of the Change Order shall have no effect on the original Agreement other than matters expressly provided herein. ATTEST: Maxwell Contractinn, Inc., P.O. Box 1998, Cocoa, Fla. 32923-1998 Contractor Date -'(Corporat~-.SeaQ (President) ,,~r2,//~/~0 (Secretary) - Date ATTEST: CITY OF SANFORD, FLORID Date Date For the use and relia of the City of Sanford only. Approved o form and legal sufficiency. Donn . Mclntosh - City Attorney As authorized by the City Commission at regular m~ting. END OF SECTION J:\S0620.04\word\cont\ch~ord2RNALwpd 00681-9