654-Wharton Smith/Reclaimed linApril 24, 1997
MEMORANDUM
To: City Manager ~'~
From: Utility Director FF?
Re: Change Order #1 - Reclaimed Line to SCC
Addition of Springview Drive
Bill -
The City Commission previously approved the CP&H engineering
proposal for the design of an additional reclaimed water line on
Springview Drive in Groveview. We now have a change order from
Wharton-Smith to construct this line.
Attached is change order #1 in the amount of $91,907.50 to
perform this work. We will be receiving a grant from the St.
Johns River Water Management District in the amount not to exceed
$48,500 or 50 % of the cost for this project.
It is recommended that the City approve this change order.
PM/ar
xc: Utility Engineer
Project Coordinator
attachment
SECTION 00681
CONTRACT CHANGE ORDER
Change Order No. 1
Project No. S0602.95
Project Title: City of Sanford Reclaimed Water Service Extension to Seminole Community College -
Phase I
Contractor: Wharton-Smith, Inc.
Reason for Change: Added a 6-inch Reclaimed Water Main and Service Lines aloncl SDrinaview Drive
Breakdown of Proposed Chanaes and Basis for Payment
(Includes pertinent drawings, specifications, and documentation where necessary. )
Change in
Unit Total Contract
Iterr ",scription Unit Qty Cost Cost Cost +(-)
26. Con'
Re. ," by 6"
S,~ n Gato I ! ! j
Eact; ~ I S2000 ~ S2000 S + 2000
27. ,inch
,aive Each 1 $1600 $1600 $ + 1600
~claimed Water
28. ' -- [/ ~ned Joints
/ LF 2100 $15 $31500 $ + 31500
lie Iron LF 50 $20 $1000 $ + 1000
29. Furnish and Install Reclaimed Water
Main with Restrained Joints
a. (~-inch PVC LF 400 $15 $6000 $ + 6000
b. 6-inch Ductile Iron LF 50 $20 $1000 $ + 1000
30. Furnish and Install Ductile Iron Fittings Ton 0.3 $7000 $2100 $ + 2100
31. Furnish and Install Gate Valves Each I $400 $400 $ + 400
32. Furnish and Install Reclaimed Water
Service Line
a. 1 -inch Tapping Saddle and
Corporation Cock Each 40 $100 $4000 $ + 4000
b. 1-inch Polyethylene Service
Line - Open-Cut LF 600 $14 $8400 $ + 8400
c. 1-inch Polyethylene Service
Line - Bore Under Pavement LF 600 $10 $6000 $ + 6000
d. 1-inch Meter Box and Curb
Stop Each 60 $90 $5400 $ + 5400
33. Asphalt Pavement Removal and
Replacement LF 65 $12.50 $812.50 $ + 812.50
34. Curb and Gutter Removal and
Replacement LF 45 $15 $575 $ + 675
A:',S0602.95\00681 .win:arb:ss 00681-1 4/97
Change in
Unit Total Contract
Item No. end Description Unit Qty Cost Cost Cost +(-)
35. Sidewalk Rernoval and Replacement LF 80 $ ! 4 $1120 I $ + 1120
36. Sodding LF 2100 $3 $6300 $ + 6300
37. Concrete Driveway Removal and
Replacement LF 500 $30 $10000 $ + 10000
38. Furnish and Install Manual Air Release
Valves Each 6 $600 $3600 $ + 3600
(1) Total Proposed Change in Contract Cost +(-) $ 91,907.50
(2) Original Contract Price $ 362,000.00
(3) Total All Previous Change Orders (Change Order No. I thru 0 ) $ 0
(4) New Contract Price (Total of Item 1 through Item 3) $ 453,907.50
(5) Original Contract Time 90 Days
(6) Additional Days Approved (Change Order No. through No.__0) 0 Days
(7) Current Contract Time 90 Days
(8) Additional Days Proposed ~ O Davs
(9) New Contract Time (Total of Items 7 and 8) / ~O Days
(10) New Construction Completion Date '-/~ /1 '~7 / ~ /~ 7
Accepted by Owner: ~ / Date: ~/-/,2 ~/' ~"7
END OF SECTION