Mr. Robert J. Walter, P.E.
City of Sanford
P O Box 1788
Sanford, Florida 32772-1788
Re: Proposal for Engineering Services
Sanford Municipal Stadium
CPH lob No. Z6582.00
Dear Mr. Walter:
We are pleased to respond to your request for a proposal for an engineering study for the Sanford
Memorial Stadium. It is our understanding that you want a study for a sum not to exceed $5,000,
and to result in an assessment of the condition of the stadium, and a cost estimate for effecting the
needed repairs to bring the stadium into original condition. The study will include a field investigation
to determine the extent of deterioration of the structure, the general condition of the electrical
service, the points of connection for sanitary and storm sewer, and the ADA access and
accommodations. We will also meet with a contractor approved by the City to discuss repair and
painting alternafxves for the stadium structure and thek associated costs. We will coordinate with the
C~ty Recreation Department to obtain their input as to the recreational functions of the facility, and
incorporate their recommendations and suggestions as to needed improvements.
We will provide the City with a report summarizing the findings of our investigation. The report will
include recommended repairs and painting procedures for the grandstand, including the roof, decking,
handrails, structural members, dugout storm drainage, plus general recommendations for electrical,
lighting, and stadium club roof. We will also include an evaluation of the stadium for ADA access
for seating and restroom facility requirements. The ADA evaluation will include a general summary
of requirements. No negotiations for alternative accommodations with any regulatory agencies will
be included such as alternative seating and restroom areas or variances, etc. We will include a
preliminary opinion of probable construction cost for the recommended improvements in the study.
The study will not include any survey, detailed drawings, structural design, or structural certification
of structure. The repair recommendations will be predicated on the assumption the original design
of the structure is sufficient for current loads and repairs will be intended to restore the structure to
its original condition.
The scope of services is further defined by the enclosed Plan of Study. We will agree to provide the
services as described for a lump sum fee of $5,000.
Conkiln, Porter and Holmes
Tft~s propos~J meets ~th your ~pp~o~, ~as~ so i~ic~t~ by sing ~ ~e~g o~ ~o~y fo~
ou~
Sincerely,
CO~ POK~K ~ HOL~S-ENG~EKS, ~C.
David A. Te~lleger, P.E.
Project M~ager
Enclosures
ACCEPTANCE:
For City of S~ord, Flo~da Date
Conkiln, Porter and Holmes
SANFORD, FLORIDA 32772-2808
TEL407-322-6841 TEL407-831~5717
FAX #40'7-330-0639
PLAN OF STUDY
H'EM DESCRIIYHON P E T D S ES'FIM,XTI.~D
E X PEN S F.S
1. Field Evaluation:
Photographics 2
Sketches, rough field 4 4
measurements
Mapping and notation of 4 4
damage
Investigate drainage system for 2 2
dugouts
Evaluate sewer connection; 1 3 -
determine methods by which
building plumbing would be
upgradod and replac~l
Evaluate main electrical service: 2 $500.00
Provide comments or need for
rewiring of concession room,
stadium club and restrooms Coy
subconsultant)
2. General evaluation of stadium for 8
ADA access and accommodations;
requirements for restrooms, emergency
lighting and exits
3. Meet with and coordinate with a 8 -
contractor or contractors to review
findings and discuss project. Obtain
input and costs and scope for the work.
4. Prepare a Summary Report to include 16 12 - 4
items listed below:
Conkiln, Porter and Holmes
SANFORD, FLORIDA 32772-2i~)8
TEL407..322-6841 TEL407-831-5717
FAX #407-330-0639
ITE31 DI:~SCRIIrrlON P E i, D S ESTIMA'FED
EXPENSES
Recommended repairs for
grandstand including roof,
decking, handrails, structural
members and stadium dub roof
Paint recommendation for
surface preparation, priming
and painting
Restroom facility requirements
for lighting plumbing and
handicap access
Concession room lighting,
plumbing and electrical
including smoke detection
Stadium dub room requirements
for lighting and electrical
Recommendations for dugout
drainage system
Costs of repair and renovation
work
TOTALS 0 45 27 0 5 $500.00
J:~OBS~Z6582.00\WI~PROFOSAL'~TAD1UM,JM8
'~'~Subject: Memorandum
To: Bill Simmons P.E., City Manager ~e
cc: Jay Marder, Director of Planning and nt
From: Robert Walter P.E., Professional Engineer ~
Per the request of the City Commission, We have requested proposals
from two Engineering Firm to conduct an "Engineering Study" of the
Sanford Memorial Stadium. Please find attached a copy of the
proposal from Conklin Porter and Holmes. Gee and Oenson Inc. has
been involved in similar work and was invited to submit a proposal,
but could not complete this study for the $5000 threshold.
Attachments:
08.'fi5'96 16r,~2 FAX 14076602852 GEE & JE,NSON ~001
;~ost~lt~FaxN0te 7671 ha~ l~tq}~ #~{ )'
b~j~ept C~,
CITY OF SANFORD
SANFORD MEMORIAL STADIUM
SCOPE OF SERVtCES
1. Conduct a cursory field examination of [he Structural Members~ Roof
Structure, Electrical and Plumbing of Grand Stand, Restrooms,
Concession Stand and Stadium Ciub and provide an opinion of the general
condition,
2 Perform a cede compliance evaluation of the above noted facilities.
3. Provide a general order of magnitude budget estimate of the costs to
refurbish the stadium,
4, Prepare a written report of findings.