947-Magnolia Ave. Change ord 1 SECTION 00950
CHANGE ORDER FORM
Change Order No.:
Project Title:
Bid No,:
Owner:
Contractor:
Agreement Date:
1
Magnolia Avenue Reclaimed Water Main Extension
IFB 01 / 02- 40
City of Sanford
Central Florida Tapping and Construction Services, Inc.
October 8, 2002
This Change Order is necessary to cover changes in the work to be
performed under this Agreement. The GENERAL CONDITIONS,
SUPPLEMENTARY CONDITIONS, and STANDARD SPECIFICATIONS
apply to and govern all work under this Change Order.
THE FOLLOWING CHANGES ARE MADE TO THE CONTRACT DOCUMENTS:
(1) Original Contract Price
(2) Current Contract Price (Adjusted By Previous Change Orders)
(3) Total Proposed Change in Contract Price
(4) New Contract Price (Item 2 + Item 3)
(5) Original Contract Time
(6) Current Contract Time (Adjusted By Previous Change Orders)
(7) Total Proposed Change in Contract Time
(8) New Contract Time (Item 6 + Item 7)
(9) Original Contract Substantial Completion Date
(10) New Contract Substantial Completion Date
$ 39,903.00
$ 39,903.00
$ 4,640.00
$ 44,543.00
75 Days
75 Days
Additional 52 Days
127 Days
December 24, 2002
February 14, 2003
SP~OLIB120902 00950-1
CHANGES ORDERED
ITEM 1
Description of Change:
Reason for Change:
Change in Contract Price:
Change in Contract Time:
Add 160 LF of 4" DR-11 polyethylene pipe to be installed by the
directional drilling method, including fusing, MJ adapters, and
service connections (approximate Sta 21+22 to Sta 22+82).
To protect 2 large oak trees (at 609 Magnolia Avenue) from
possible root damage due to pipe installation by open-cut
methods.
Additional $6,080.00.
No change.
ITEM 2
Description of Change:
Reason for Change:
Change in Contract Price:
Change in Contract Time:
Delete 160 LF of 4" DR-18 PVC pipe to be installed by open-cut
methods.
Replaced by Item 1 above.
Deduct $1,440.00.
No change.
ITEM 3
Description of Change:
Reason for Change:
Time adjustment.
To postpone the reclaimed water main construction until after the
holidays because of the "Holiday Tour of Homes".
Change in Contract Price: No change.
Change in Contract Time: Additional 52 days.
SPECLIB120902 00950'2
CHANGE ORDER SUMMARY
No. I Description t ~Change in I Change in
~,ontract Price Contract Time
Add 160 LF of 4" DR-11 polyethylene
1 pipe, installed by directional drilling. $6,080.00 No change
Deduct 160 LF of 4" DR-18 PVC pipe,
2 installed by open-cut. ($1,440.00) No change
3 Add 52 days to Contract Time No change Add 52 days
TOTAL $4,640.00 52 Days
WAIVER This Change Order constitutes full and mutual accord and satisfaction for the
adjustment of the Contract Price and Contract Time as a result of increases or decreases in
cost and time of pedormance caused directly and indirectly from the change. Acceptance of
this Waiver constitutes an agreement between OWNER and CONTRACTOR that the Change
Order represents an equitable adjustment to the Agreement and that CONTRACTOR shall
waive all rights to file a Contract Claim or claim of any nature on this Change Order. Execution
of this Change Order shall constitute CONTRACTOR's complete acceptance and satisfaction
that it is entitled to no more costs or time (direct, indirect, impact, etc.) pursuant to this Change
Order.
SPECLIB120902 00950'3
APPROVAL AND CHANGE ORDER AUTHORIZATION
ACKNOWLEDGMENTS
The aforementioned change, and work affected thereby, is subject to all provisions of the
original Agreement and specifically changed by this Change Order; and
It is expressly understood and agreed that the approval of the Change Order shall have no
effect on the original Agreement other than matters expressly provided herein.
ATTEST:
Central Florida Tappinq &
Construction Services, Inc.
(Secretary)
Date I '
(Corporate Seal)
Printed Name and Title of,O'ffid'er'
By (Signature)
Date
ATTEST:
~ignature)
Cate
(Seal)
City of Sanford
END OF SECTION
SPECLiB120902 00950-4
~ · Central Florida T~pping &
[] · ~c~ion Ser,~[~es, ]pc.
CU C055705
C0 C045852
CONT V 139429000119?
January 10, 2003
Tom Zinker, P.E.
CPH Engineers
P.O. Box 2828
Sanford, FI. 32722-2808
Re: Proposed Cha~ge
;Dear M~, Zinkcr,
We propose the following,
Item
~ DeecHpfion Quanti~ Unit Unit Price Tolal
1 Add 4" SDR-11 including Fusing 160 LF $ 3800 $ 6,080 00
and MJ adapters
2 Deduct 4" DR-lB PVC 160 LF $ (900) $ (1,~40.00)
Totll Addition $
If the City wants to make ~kis change the pipe is in Tampa and may rake a couple of days
to get here. If you have any questions please call.
Sincerely,
Kicg Bullington
P.O. Box 521279 · Longwoocl, FL 32752-1279 - Phone: 407-834-8271 - Fax: 407-834-3859